Ind. Code § 36-7-11-12
(b) If an application for a certificate of appropriateness:
(2) is not acted on by the commission;
within thirty (30) days after it is filed, a certificate of appropriateness shall be issued. If the certificate is issued, the application shall be processed in the same manner as applications for building or demolition permits required by the unit, if any, are processed. If no building or demolition permits are required by the unit, the applicant may proceed with the work authorized by the certificate.
(d) The commission may grant an extension of the thirty (30) day limit prescribed by subsections (b) and (c) if the applicant agrees to it.
[Pre-Local Government Recodification Citation: 18-7-22-9.]
As added by Acts 1981, P.L.309, SEC.30. Amended by P.L.227-1997, SEC.13.