Ind. Code § 22-5-1.7-17

Termination of contract with subcontractor for violation of chapter; action to challenge

As added by P.L.171-2011, SEC.16. Amended by P.L.6-2012, SEC.158.
  1. (a) If a contractor determines that a subcontractor is in violation of this chapter, the contractor may terminate a contract with the subcontractor for the violation.
  2. (b) The termination of a contract under subsection (a) for a violation of this chapter by a subcontractor may not be considered a breach of contract by the contractor or the subcontractor.
  3. (c) A subcontractor may file an action with a circuit or superior court having jurisdiction in the county to challenge a termination of a contract under subsection (a) not later than twenty (20) days after the contractor terminates the contract with the subcontractor.

As added by P.L.171-2011, SEC.16. Amended by P.L.6-2012, SEC.158.