Ind. Code § 22-5-1.7-14
A contractor may file an action with a circuit or superior court having jurisdiction in the county to challenge:
(2) a termination of a:
(B) contract for a public works project under section 13(a) of this chapter not later than twenty (20) days after the public agency terminates the contract for the public works project with the contractor;
whichever is applicable.
As added by P.L.171-2011, SEC.16. Amended by P.L.252-2015, SEC.35.