Ind. Code § 16-29-2-6
Certificate of need voidable; conditions
As added by P.L.2-1993, SEC.12. Amended by P.L.1-1993, SEC.170.
A certificate of need for a project to construct, add, or convert beds that receives final approval of the state department under this chapter or IC 16-10-4 (before its repeal) becomes void eighteen (18) months after the determination becomes final unless the following conditions are met:
- (1) Construction plans for the project are approved by the state department and the department of fire and building safety.
- (2) The applicant has completed construction of the project's foundation in conformity with the approved plans as certified by an independent architect licensed under IC 25-4 or an independent professional engineer licensed under IC 25-31 .
(3) Construction work on the project is continuous and in conformity with the approved plans.
[Pre-1993 Recodification Citation: 16-10-4-9.5(f).]
As added by P.L.2-1993, SEC.12. Amended by P.L.1-1993, SEC.170.