Ind. Code § 14-39-2-5.5
Draft permit
As added by P.L.161-2026, SEC.58.
(a) Upon determining that an application is complete, the department must decide whether to:
- (1) prepare a draft permit for the public comment process; or
(2) deny the application.
The department shall notify the applicant of the decision.
(b) If the department decides to prepare a draft permit, the permit must contain the following:
- (1) Conditions of the permit.
- (2) Compliance schedules.
- (3) Monitoring requirements.
(c) Within seven (7) days after receiving the completed application, the department shall prepare and provide to the applicant a project decision schedule that specifies target dates by which the department intends to:
- (1) prepare a draft permit;
- (2) give public notice;
- (3) complete the public comment period, including any public hearing; and
- (4) issue a final permit.
- (d) The department may not deny an application without a public comment period and hearing.
- (e) The department shall adopt rules that mirror applicable federal regulations to implement this section.
As added by P.L.161-2026, SEC.58.