As added by P.L.1-1995, SEC.23.

The commission may adopt rules to do the following:

  1. (1) Require that increased water runoff resulting from new construction be impounded on the construction site.
  2. (2) Permit the waiver of requirements of onsite water impoundment on payment of a reasonable fee by the developer of the new construction.

    [Pre-1995 Recodification Citation: 36-7-6.1-19.]