- (a) An application for a permit for a hazardous waste treatment, storage, or disposal facility must include a closure plan. If hazardous waste is to be disposed of at the facility, the application must also include a postclosure monitoring and maintenance plan.
(b) The closure plan required under subsection (a) must include at a minimum the following:
- (1) An estimate of the cost of closure.
- (2) A description of the method of closure.
- (3) Possible uses of the land after closure.
- (4) Anticipated time before closure.
- (5) An estimate of time to complete closure.
(c) The postclosure monitoring and maintenance plan required under subsection (a) must include at a minimum the following:
- (1) An estimate of the cost of postclosure monitoring and maintenance for a period of thirty (30) years.
(2) A description of the system to be employed for security, groundwater and leachate monitoring, sampling analysis, and periodic reporting.
[Pre-1996 Recodification Citation: 13-7-8.5-5.1(a), (b), (c).]
As added by P.L.1-1996, SEC.12.