(a) Before the issuance of a request for proposals under this chapter, the board must do the following:
- (1) Adopt a proposed request for proposals by resolution.
- (2) Publish a public notice that may contain a request for qualifications if a prequalification process has been adopted under section 3 of this chapter, including the criteria on which proposers may be selected.
(b) The public notice must do the following:
- (1) Include the intent to issue a request for proposals.
- (2) Designate times and places where the proposed request for proposals may be viewed by the general public.
- (3) State the time of commencement of the thirty (30) day period established in this section, which constitutes the event referred to in IC 5-3-1-2 .
(c) The board shall allow not more than a thirty (30) day period for the following:
- (1) The submission of qualifications, if required.
- (2) Comments on the proposed request for proposals.
(d) After the thirty (30) day period described in subsection (c) expires, the board shall do the following:
- (1) Select at least one (1) proposer.
- (2) Adopt a request for proposals.
- (e) Comments may be addressed to the scope or contents of the proposed request for proposals.
(f) The board shall do the following:
- (1) Notify each proposer of their selection.
- (2) Inform each proposer of the date and place proposals are to be submitted.
(3) Deliver to each proposer a copy of the request for proposal.
[Pre-1996 Recodification Citation: 13-9.5-8-3(2).]
As added by P.L.1-1996, SEC.11.