Ind. Code § 13-20-2-9

Requirement resulting from inaction on construction permit

As added by P.L.205-2007, SEC.1.
  1. (a) A person that:

    1. (1) holds a valid construction permit that is issued under this chapter and authorizes construction for a facility that has not been substantially developed; and
    2. (2) has not commenced construction within:

      1. (A) five (5) years after the date of the permit; or
      2. (B) another period established by rule or statute;

        must apply for a new construction permit and meet the requirements of all applicable environmental laws existing at the time the new permit is sought.

  2. (b) A person that:

    1. (1) holds a valid construction permit that is issued under this chapter and authorizes construction at an operating facility; and
    2. (2) has not commenced construction within:

      1. (A) five (5) years after the date of the permit; or
      2. (B) another period established by rule or statute;

        must meet the requirements of all applicable environmental laws existing at the time construction is substantially commenced.

  3. (c) The periods described in subsections (a) and (b) for a person to commence construction are tolled pending either of the following concerning the construction permit:

    1. (1) An administrative appeal.
    2. (2) A judicial review.

As added by P.L.205-2007, SEC.1.