Ill. Admin. Code tit. 92, § 530.500
b) Boring or Jacking
c) Trenching
d) Backfilling
e) Pavement Cuts
Pavement cuts for utility installation or repair will not be permitted on any State highway open for traffic. If a variance is permitted in accordance with Section 530.130, the following requirements shall apply:
f) Material Storage on Right-of-Way
All pipe, conduit, wire, poles, cross arms or other materials distributed along the highway prior to installation shall be placed as remotely as practicable from the edge of pavement in a manner to minimize its being a hazard to errant vehicles or an obstacle to highway maintenance and not in the clear zone. If material is to be stored on highway right-of-way for more than two weeks prior to installation, approval must be obtained from the Department as defined in Section 530.30.
g) Operational Restrictions