Ill. Admin. Code tit. 83, § 467.APPENDIX F
8. The interconnection customer shall pay any actual study costs that exceed the deposit within 30 calendar days after receipt of the invoice. The EDC shall refund any excess deposit amount within 30 calendar days after the invoice.
In witness whereof, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written.
[Insert name of interconnection customer]
| Signed: | |||||
| Name (Printed): | Title: | ||||
[Insert name of EDC]
| Signed: | |||||
| Name (Printed): | Title: | ||||
Attachment A to Interconnection Facilities Study Agreement
Minimum Information that the Interconnection Customer Must Provide
with the Interconnection Facilities Study Agreement
Provide location plan and simplified one-line diagram of the distributed generation facilities.
For staged projects, please indicate size and location of planned additional future generation.
On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT/PT)
On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps
One set of metering is required for each generation connection to the EDC's electric distribution system.
| Number of generation connections: |
Will an alternate source of auxiliary power be available during CT/PT maintenance?
| Yes | No |
Will a transfer bus on the generation side of the metering require that each meter set be designed for the total distributed generation capacity?
| Yes | No | (Please indicate on the one-line diagram.) |
| What type of control system or PLC will be located at the distributed generation facility? | ||
| What protocol does the control system or PLC use? | ||
Please provide a scale drawing of the site. Indicate the point of common coupling, distribution line, and property lines.
| Number of third party easements required for EDC's interconnection facilities: |
To be completed in coordination with EDC.
Is the distributed generation facility located in EDC's service area?
| Yes | No | |||
| If No, please provide name of local provider: | ||||
Please provide the following proposed schedule dates:
| Begin Construction Date: | |||||||
| Generator Step-up Transformers Receive Back Feed Power Date: | |||||||
| Generation Testing Date: | |||||||
| Commercial Operation Date: | |||||||
Interconnection Facilities Study Agreement
| This agreement ("Agreement") is made and entered into this | day of | |||||||||||
| by and between | ("interconnection customer"), as an | |||||||||||
| individual person, or as a | organized and existing under the | |||||||||||
| laws of the State of | , and | ("Electric Distribution | ||||||||||
| Company" (EDC)), a | existing under the laws of the | |||||||||||
| State of Illinois. Interconnection customer and EDC each may be referred to as a "Party", or collectively as the "Parties". | ||||||||||||
Recitals:
Whereas, the interconnection customer is proposing to develop a distributed generation facility or modify an existing distributed generation facility consistent with the interconnection request
| application form submitted by the interconnection customer on | (Date) | ; and |
Whereas, the interconnection customer desires to interconnect the distributed generation facility with the EDC's electric distribution system; and
Whereas, the EDC has completed an interconnection system impact study and provided the results of that study to interconnection customer; and
Whereas, the interconnection customer has requested the EDC to perform an interconnection facilities study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to interconnect the distributed generation facility;
Now, therefore, in consideration of and subject to the mutual covenants contained in this Agreement, the Parties agree as follows: