Ill. Admin. Code tit. 83, § 467.APPENDIX E
5. The interconnection system impact study report shall provide the following information:
9. The interconnection customer shall pay any study costs that exceed the deposit within 30 calendar days after receipt of the invoice. EDC shall refund any excess deposit amount within 30 calendar days after the invoice.
In witness thereof, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written.
[Insert name of interconnection customer]
| Signed: | |||||
| Name (Printed): | Title: | ||||
[Insert name of EDC]
| Signed: | |||||
| Name (Printed): | Title: | ||||
Attachment A to Interconnection System Impact Study Agreement
Assumptions Used in Conducting the Interconnection System Impact Study
The interconnection system impact study shall be based upon the results of the interconnection feasibility study, subject to any modifications in accordance with Section 467.70 of the Illinois Distributed Generation Interconnection Standard, and the following assumptions:
Point of interconnection and configuration to be studied to the extent it is different from the information provided in the application or feasibility study.
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Note: This Attachment A is to be completed by mutual agreement of the Parties. Any additional assumptions (explained below) may be provided by either the interconnection customer or the EDC.
______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
5.1 Identification of any equipment short circuit capability limits exceeded as a result of the interconnection;
5.2 Identification of any thermal overload or voltage limit violations resulting from the interconnection;
5.3 Identification of any instability or inadequately damped response to system disturbances resulting from the interconnection; and
5.4 Description and non-binding estimated cost of facilities required to interconnect the distributed generation facility to EDC's electric distribution system and to address the identified short circuit, thermal overload, voltage and instability issues, as required under Section 467.70(e)(2) of the Illinois Large Distributed Generation Interconnection Standard.
Interconnection System Impact Study Agreement
| This agreement ("Agreement") is made and entered into this | day of | |||||||||||
| by and between | ("interconnection customer"), as an | |||||||||||
| individual person, or as a | organized and existing under the | |||||||||||
| laws of the State of | , and | ("Electric Distribution | ||||||||||
| Company" (EDC)), a | existing under the laws of the | |||||||||||
| State of Illinois. Interconnection customer and EDC each may be referred to as a "Party", or collectively as the "Parties". | ||||||||||||
Recitals:
Whereas, the interconnection customer is proposing to develop a distributed generation facility or modify an existing distributed generation facility consistent with the interconnection request
| application form completed by interconnection customer on | (Date) | ; and |
Whereas, interconnection customer desires to interconnect the distributed generation facility to the EDC's electric distribution system; and
Whereas, the EDC has completed an interconnection feasibility study and provided the results of the study to the interconnection customer (this recital to be omitted if the Parties have agreed to forego the interconnection feasibility study); and
Whereas, the interconnection customer has requested the EDC to perform an interconnection system impact study to assess the impact of interconnecting the distributed generation facility to the EDC's electric distribution system;
Now, therefore, in consideration of and subject to the mutual covenants contained in this Agreement the Parties agree as follows: