Ill. Admin. Code tit. 83, § 285.2060 – Schedule B-7.1: Construction Work in Progress Percent Complete | Midpage
§ 285.2060
Ill. Admin. Code tit. 83, § 285.2060
Schedule B-7.1: Construction Work in Progress Percent Complete
AUTHORITY: Implementing Sections 9-201, 16-108, and 16-108.5 and authorized by Section 10-101 of the Public Utilities Act [220 ILCS 5/9-201, 16-108, 16-108.5 and 10-101].ILLINOIS COMMERCE COMMISSION
a) For the projects identified in Schedule B-7, provide information to determine the estimated percent complete, or for a future test year, expected to be complete, at the end of the test year.
b) Information provided shall include:
1) Project number;
2) Description of project;
3) Date project started;
4) Most recent estimated project completion date;
5) Original budget estimate;
6) Most recent revised estimate;
7) Accumulated construction costs; and
8) Percent complete (the amount in subsection (b)(7) divided by the amount in subsection (b)(6) x 100).