Ill. Admin. Code tit. 77, § 855.170
a) Project Manager
1) The project manager shall be licensed by the Department in accordance with Section 855.100. For asbestos abatement projects in schools, the project manager shall be the building owner's designated representative, and shall be responsible for carrying out the following activities:
5) For each asbestos abatement project, the project manager shall prepare a comprehensive final report. The report shall be submitted to the school board or building owner, the contractor, and the Department within 60 working days following completion of final clearance air monitoring. The report shall contain the following items submitted in the following order, with each item labeled:
C) For clearance air samples, the location of the sample, date of sample, start and end times of sampling, sampling air flow rate, volume of air sampled, name and address of laboratory performing the analysis, and name and signature of the analyst.
b) Air Sampling Professional (ASP)
2) Area sampling shall be conducted using collection media and procedures in accordance with NIOSH method 7400. The following schedule shall be utilized for air sampling during the project in addition to any OSHA compliance monitoring required to be conducted by the contractor:
B) The following schedule of samples shall be required on a daily basis once abatement activities begin. The size of the abatement activity will have impact on the number of samples necessary to monitor the contractor's activities. The following are required minimums:
c) Analyst Services
d) Project Manager/Air Sampling Professional Duties Combined
The project manager and air sampling professional shall be two separate individuals for each contained area. Duties may only be combined for abatement project activities when the contained area is less than or equal to 10,000 square feet or less than or equal to 1,500 linear feet of pipe insulation in one contained area and decontamination enclosure system.