Ill. Admin. Code tit. 44, § 1.2030
a) Authority to Make Emergency Procurements
The provisions of this Part apply to every procurement over the small purchase limit set in Section 1.2020 (Small Purchase Limits) made under emergency conditions. The SPO, or a State agency through written designation, shall have the authority to make emergency procurements when an emergency condition arises and the need cannot be met through normal procurement methods.
b) Emergency Conditions
1) A statutory emergency condition exists:
c) Quick Purchase
The emergency method of source selection is allowed in additional situations. These include, but are not limited to:
1) protect the health and safety of any person;
d) Scope of Emergency Conditions
Emergency procurement shall be limited to the supplies, services, construction or other items necessary to meet the emergency need. In certain situations the purchase to meet the immediate need (i.e., the temporary solution) may, by necessity, also be the permanent solution. In this event, the notice shall describe that circumstance.
e) Source Selection Methods
Any method of source selection, whether or not identified in this Part, may be used to conduct the procurement in emergency situations provided that, whenever practical, existing State contracts shall be utilized and competitive sources shall be considered if practical. The procedure used shall be selected to assure that the required items are procured in time to meet the emergency. Such competition as is practicable shall be obtained.
f) Determination and Record of Emergency Procurement
2) Emergency Contract Award
A) For purposes of an emergency, an emergency contract is awarded on the earliest of the date:
3) Record. In a manner acceptable to the receiving parties, the CPO-GS shall designate the method of filing statements of each emergency procurement with the PPB and Auditor General. An affidavit of each emergency procurement (including extensions of emergency contracts beyond 90 days) shall be filed by the SPO with the CPO-GS, PPB and the Auditor General within 10 days after the contract is awarded and shall include the following information:
4) Notice of the Emergency Procurement
Notice of the emergency procurement shall be published in the Bulletin by the SPO as specified in Sections 15-25(c) and 20-30 of the Code no later than 5 days after the contract is awarded and shall include a description of the procurement, the reasons for the emergency procurement and the total cost. When only an estimate of the total cost is known at the time of publication, the estimate shall be identified as an estimate and published. When the total cost is determined, it shall also be published in like manner before the 10th day of the next succeeding month.
g) Duration of Emergency Contract
3) Notice of Extension
Notice of intent to extend an emergency contract shall be published in the Bulletin no later than 14 days prior to a public hearing. Notice shall include at least a description of the need for the emergency extension, the contractor, and, if applicable, the date, time and location of the public hearing.
h) Contract Extension Hearing
The hearing shall be conducted in accordance with Subpart V.
(Source: Amended at 46 Ill. Reg. 10208, effective June 2, 2022)