Ill. Admin. Code tit. 35, § 310.705
Factors that are Not Fundamentally Different
Effective Mar 23, 202347 Ill. Reg. 5083AUTHORITY: Implementing and authorized by Sections 7.2, 13, 13.3, and 27 of the Environmental Protection Act [415 ILCS 5/7.2, 13, 13.3, and 27].POLLUTION CONTROL BOARD
- a) The feasibility of installing the required waste treatment equipment within the time the federal CWA (33 U.S.C. 1251 et seq.), incorporated by reference in Section 310.107(c), allows;
- b) The assertion that the standards cannot be achieved with the appropriate waste treatment facilities installed, if that assertion is not based on factors listed in Section 310.704;
- c) The industrial user's ability to pay for the required waste treatment; or
d) The impact of a discharge on the quality of the POTW's receiving waters.
BOARD NOTE: Derived from 40 CFR 403.13(e) (2005).
An FDF request or portion of such a request under this Subpart G must not be granted on any of the following grounds:
(Source: Amended at 47 Ill. Reg. 5083, effective March 23, 2023)