- a) The owner or operator of an emission source subject to Section 215.405(a)(1) shall submit to the Agency a compliance plan, pursuant to 35 Ill. Adm. Code 201, Subpart H, including a project completion schedule where applicable, no later than April 21, 1983.
- b) The owner or operator of an emission source subject to Section 215.405(b) shall submit to the Agency a compliance plan, including a project completion schedule where applicable, no later than December 31, 1986.
- c) The owner or operator of an emission source subject to Section 215.405(c) shall submit a compliance plan, including a project completion schedule within 90 days after the date of redesignation, but in no case later than December 31, 1986.
- d) Unless the submitted compliance plan or schedule is disapproved by the Agency, the owner or operator of a facility or emission source subject to the rules specified in subsections (a), (b) or (c) may operate the emission source according to the plan and schedule as submitted.
- e) The plan and schedule shall meet the requirements of 35 Ill. Adm. Code 201, Subpart H, including specific interim dates as required in 35 Ill. Adm. Code 201.242.
(Source: Amended at 11 Ill. Reg. 16706, effective September 30, 1987)