Ill. Admin. Code tit. 35, § 215.APPENDIX C
3) Any compliance plan or project completion schedule, where applicable, shall be a binding condition of the operating permit for the source.
Rule 104(g)
Compliance Programs and Project Completion Schedules –
Submission and Approval Dates
The owner or operator of an emission source subject to the following rules shall have a Compliance Plan and a Project Completion Schedule, where applicable, approved by the Agency by the following dates. A Compliance Plan and a Project Completion Schedule, where applicable, shall be submitted at least 90 days before the following dates.
4) By April 1, 1980. Coating lines subject to Rule 205(n), except (n)(1)(J), and (K). Bulk gasoline plants, bulk gasoline terminals and petroleum liquid storage tanks subject to Rule 205(o), except (o)(3), which are located in counties other than Cook, Lake, DuPage, Kane, McHenry or Will.
Rule 104(h)
Compliance Programs and Project Completion Schedules –
RACT II Compliance Plan Submission and Approval
1) The owner or operator of an emission source subject to Rule 205(j)(1) shall submit to the Agency a compoiance plan, including a project completion schedule where applicable, no later than:
| Rule | Days After Promulgation | |
| (A) | Rules 205(o)(3), 205(s) and 205(t) | 90 |
| (B) | Rules 205(u)(1)(A) and (B) | 90 |
| (C) | Rule 205(n)(1)(J) and (K) | 210 |
5) The plan and schedule shall meet the requirements of Rule 104(b) including specific interim dates as required in Rule 104(b)(2).
Rule 205(j)
Compliance Dates
1) Except as otherwise stated in subsection (2), every owner or operator of an emission source shall comply with the standards and limitations of Rule 205 in accordance with the dates shown in the following table:
| Rule | Type of Source | Compliance Date |
| 205(a) - (i) | New Emission Sources | April 14, 1972 |
| 205(a) - (i) | Existing Emission Sources | December 31, 1973 |
| 205(k) | All Emission Sources | July 1, 1980 |
| 205(l)(1)-(3) | All Emission Sources | July 1, 1980 |
| 205(l)(4) - (10) | All Emission Sources | See Rule (m) |
| 205(n) | All Emission Sources | December 31, 1982* |
| 205(n)(1)(J) and (K) | All Emission Sources | December 31, 1983 |
| 205(n)(1)(K)(ii) | All Emission Sources | See Rule 205(m)(5) |
| 205(o)(1) and (2) | All Emission Sources | July 1, 1981 |
| (o)(3) | ||
| 205(p) | All Emission Sources | See rule 205(m) |
| 205(q) | All Emission Sources | December 31, 1980 |
| 205(s) and (t) | All Emission Sources | December 31, 1983 |
| 205(u)(1)(A)-(C) | All Emission Sources | December 31, 1983 |
| 205(u)(1)(D)-(G) | All Emission Sources | May 1, 1983 |
*Except for automobile and light-duty truck manufacturing plants achieving final compliance under a footnote to Rule 205(n)(1).
2) If an emission source is not located in one of the counties listed below** and is also not located in any county contiguous thereto, the owner or operator of the emission source shall comply with the requirements of rule 205(1)(4)-(10), (n)(1)(J) or (K), (o)(3), (s), (t), or (u) no later than December 31, 1987:
| Cook | Macoupin |
| DuPage | Madison |
| Kane | Monroe |
| Lake | Saint Clair |
3) Notwithstanding subsection (2) above, if any county is designated as non-attainment by the U.S. Environmental Protection Agency at any time subsequ3nt to the effective date of this Rule, the owner or operator of an emissin source located in that county or any county contiguous to that county who would otherwise be subject to the compliance date in subsection (2) shall comply with the requirements of Rule 205(1)(4)-(10), (n)(1)(J) or (K), (o)(3), (s), (t), or (u) within one year from the date of redesignation but in no case later than December 31, 1987.
** These counties are proposed to be designated as nonattainment by the U.S. Environmental Protection Agency in Federal Register, Volume 47, page 31588 (July 21, 1982).
Rule 205(m)
Compliance Schedules
The requirements of this section shall not apply to any source for which a Project Completion Schedule has been submitted to and approved by the Agency under Rule 104. The owner of any emission source subject to the requirements of this section shall certify to the Agency by January 15 of each year beginning January 15, 1980, whether increments of progress required to be met in the previous year have been met.
1) Coating Lines
C) For sources that, under the approved Compliance Plan, will comply with Rule 205(n) by installing emissin control equipment, the following increments of progress shall be met:
The owner or operator of coating lines subject to the requirements of Rule 205(n), except (n)(1)(J) and (K), shall take the following actions:
(A) Submit to the Agency a Compliance Program that meets the requirements of Rule 104(b)(1) by January 1, 1980.
(B) For sources that, under the approved Compliance Plan, will comply with Rule 205(n) by use of low solvent coating technology the following encrements of progress, shall be met:
(i) Submit to the Agency by July 1, 1980 and every six months there after a report describing in detail the progress in the previous six months in the development, application testing, product quality, customer acceptance and FDA or other government agency approval of the low solvent coating technology.
2) Bulk Gasoline Plants, Bulk Gasoline Terminals, Petroleum Liquid Storage Tanks
The owner of an emission source subject to the requirements of Rule 205(o), except (o)(3), shall take the following actions:
3) Gasoline Dispensing Facilities
Owners of gasoline dispensing facilities subject to the requirements of Rule 205(p) shall take the following actions:
4) Petroleum Refinery Leaks
The owner or operator of a petroleum refinery shall adhere to the increments of progress contained in the following schedule:
5) Coating Lines Subject to Rule 205(n)(1)(K)(ii)
B) Meet the following increments of progress:
The owner or operator of coating lines subject to Rule 205(n)(1)(k)(ii) may in lieu of compliance with Rule 205(j)(1) demonstrate compliance through the use of a low solvent coating technology by taking the following actions:
6) Rotogravure and Flexography Low Solvent Ink Alternative Compliance Plan
A) Submit to the Agency a Compliance Plan, including a compliance schedule, by December 31, 1983 which demonstrates:
B) Certify to the Agency that
The owner or operator of an emission source subject to Rule 205(s) may in lieu of compliance with Rules 104(h)(1)(A) and 205(j) demonstrate compliance through the use of a low solvent ink program by taking the following actions:
Prior to codification, compliance programs, project completion schedules, compliance dates and compliance schedules for all sources were regulated by Rules 104(a), 104(g), 109(h), 205(j) and 205(m). Past compliance date rules have been deleted from the text of the codified rules; future compliance date rules have been grouped with the rules governing the type of source. As an aid to the public, the old text of the compliance date rules are set out at length in this Appendix.
Rule 104(a)
Compliance Programs and Project Completion Schedules – Applicability
(1) No person shall cause or allow the operation of an emission source which is not in compliance with the requirements of Rule 205(k) unless such person is in compliance with a compliance program as provided for in Rule 104(g) or (h) or Rule 205(m).