Ill. Admin. Code tit. 35, § 1100.525
Procedures for Closure
Effective Aug 27, 201236 Ill. Reg. 13892AUTHORITY: Implementing Sections 5, 3.160, 22.51, and 22.51a and authorized by Sections 3.160, 22.51, 22.51a, and 27 of the Environmental Protection Act [415 ILCS 5/5, 22.51, 22.51a, and 27].POLLUTION CONTROL BOARD
a) Notification of Closure
The owner or operator must provide written notification to the Agency within 30 days after the owner or operator begins closure in accordance with the closure plan required by Section 1100.510(h) and the closure requirements of Section 1100.208.
b) Certification of Closure
- 1) Documentation concerning closure of the facility, including, but not limited to, plans or diagrams of the facility as closed and the date closure was completed.
- 2) An affidavit by the owner or operator and the seal of a PE or PG that the facility has been closed in accordance with the closure plan required by Section 1100.510(h) and the closure requirements of Section 1100.208.
When the closure of the facility is complete, the owner or operator must submit to the Agency:
(Source: Added at 36 Ill. Reg. 13892, effective August 27, 2012)