a) The records an owner or operator must maintain concerning its RAP. An owner or operator is required to keep records of the following:
2) Any operating or other records the Agency requires an owner or operator to maintain as a condition of the RAP.
BOARD NOTE: Subsection (a) is derived from 40 CFR 270.210 (2002).
b) How time periods in the requirements in Subpart H of this Part and the RAP are computed.
4) Whenever a party or interested person has the right to or is required to act within a prescribed period after the service of notice or other paper upon him by mail, four days may not be added to the prescribed term. (For example, if an owner or operator wishes to appeal the Agency's decision to modify its RAP, then the owner or operator must petition the Board within 35 days after the Agency has issued the final RAP decision.)
BOARD NOTE: Subsection (b) is derived from 40 CFR 270.215 (2002). Federal subsections (c) and (d) provide that a RAP is effective 30 days after the Agency notice of approval. The Board has used 35 days to be consistent with the 35 days within which a permit appeal must be filed under Section 40(a)(1) of the Act [415 ILCS 5/40(a)(1)]. Further, federal subsection (d) provides three days for completion of service by mail. The addition of four days (see procedural rule 35 Ill. Adm. Code 101.144(c)) to be consistent with 40 CFR 270.215(d) would exceed the 35 days allowed under Section 40(a)(1) of the Act [415 ILCS 5/40(a)(1)].
c) How an owner or operator may transfer its RAP to a new owner or operator.
2) When a transfer of ownership or operational control occurs, the old owner or operator must comply with the applicable requirements in Subpart H of 35 Ill. Adm. Code 724 (Financial Requirements) until the new owner or operator has demonstrated that it is complying with the requirements in that Subpart. The new owner or operator must demonstrate compliance with Subpart H of 35 Ill. Adm. Code 724 within six months after the date of the change in ownership or operational control of the facility or remediation waste management site. When the new owner or operator demonstrates compliance with Subpart H of 35 Ill. Adm. Code 724 to the Agency, the Agency must notify the former owner or operator that it no longer needs to comply with Subpart H of 35 Ill. Adm. Code 724 as of the date of demonstration.
BOARD NOTE: Subsection (c) is derived from 40 CFR 270.220 (2002).
d) What the Agency must report about noncompliance with RAPs. The Agency must report noncompliance with RAPs according to the provisions of 40 CFR 270.5 (Noncompliance and Program Reporting by the Director), incorporated by reference in 35 Ill. Adm. Code 720.111(b).
BOARD NOTE: Subsection (d) is derived from 40 CFR 270.225 (2005).
(Source: Amended at 30 Ill. Reg. 2845, effective February 23, 2006)