AUTHORITY: Implementing Section 17 and authorized by Section 27 of the Illinois Environmental Protection Act [415 ILCS 5/17 and 27].POLLUTION CONTROL BOARD
a) A community water supply that first commenced construction after July 26, 2019, must develop and submit a source water protection plan simultaneously with the construction permit application.
b) A community water supply in existence as of July 26, 2019, must develop and submit to the Agency for approval a source water protection plan within the following time frame after July 26, 2019:
1) within 3 years, for a community water supply serving a population greater than 50,000 persons;
2) within 4 years, for a community water supply serving a population of greater than 3,000 but less than or equal to 49,999 persons; or
3) within 5 years, for a community water supply serving a population of less than or equal to 2,999 persons.
c) An existing community water supply that anticipates using a new source of water for its supply must develop and submit a revised source water protection plan simultaneously with the construction permit application.