- a) This Section implements the permit-by-rule program provided for in Section 39.12 of the Act for classes of community water supply operating permits. By fulfilling all of the requirements of this Section, a community water supply is considered to have met the requirements for obtaining an operating permit under Section 18(a)(3) of the Act and Section 602.300.
- b) A community water supply is eligible to obtain an operating permit-by-rule if the construction project for which the Agency granted a construction permit is for any of the following projects:
1) Water main extensions; or
- 2) Projects not requiring disinfection specified in Section 602.315.
- c) A community water supply is not eligible to obtain an operating permit-by-rule if the construction project involves a water main that connects two or more community water supplies.
- d) Upon issuance of a construction permit, the Agency may notify an eligible community water supply that it may not seek a permit-by-rule if the community water supply has failed to submit the information required by Agency or Board rules in the two years preceding the Agency's notification.
- e) For construction projects that contain both permit-by-rule eligible and non-eligible components, a community water supply may obtain a partial operating permit-by-rule for the eligible portions of the project.
- f) A community water supply eligible for a permit-by-rule under subsection (b) that does not elect to obtain a permit-by-rule, must obtain an operating permit issued by the Agency before commencing operations.
g) Permit-by-Rule Certification. Any community water supply seeking to obtain an operating permit-by-rule must submit a certification, on Agency forms, specifying the following:
- 1) the community water supply's name, address, identification number and project name;
- 2) the construction permit number, type of construction permit, and date the construction permit was issued;
- 3) an explanation of the status of the construction project and, if the project is only partially completed, the information set forth in Section 602.320;
- 4) a statement attesting to compliance with Section 602.310, if disinfection is required; and
- 5) the submission of the water sample results required by Section 602.310.
- h) The community water supply may begin operation of a permit-by-rule eligible construction project immediately after it files the certification required by subsection (g).
(Source: Amended at 47 Ill. Reg. 7449, effective May 16, 2023)