a) If all phases of a construction project will not be completed at one time, the Agency must issue a partial operating permit under Section 602.105 upon receipt of:
- 1) a cover letter describing which sections of the project are completed;
- 2) a general layout plan sheet of the project indicating the location of water mains, treatment processes, or storage facilities to be operated;
3) a completed and signed operating permit application; and
- 4) bacteriological analysis results from water samples collected from the completed section of the project verifying satisfactory disinfection in accordance with Section 602.310.
- b) Additional operating permits may be obtained in accordance with this Section as other portions of the project are completed.
(Source: Amended at 47 Ill. Reg. 7449, effective May 16, 2023)