Ill. Admin. Code tit. 35, § 351.202 – Requirements of a Petition | Midpage
§ 351.202
Ill. Admin. Code tit. 35, § 351.202
Requirements of a Petition
AUTHORITY: Authorized by Sections 4(m), 4(n) and 39 of the Environmental Protection Act (Ill. Rev. Stat. 1979, ch. 111½, pars. 1004(m), 1004(n) and 1039) and implementing Section 303(e) of the Clean Water Act (33 U.S.C. 1313 (3)).ENVIRONMENTAL PROTECTION AGENCY
a) A petition filed under these rules shall include, as applicable:
1) A clear, complete and concise statement of the revision(s) sought;
2) If the petition is for a planning boundary change, it shall include:
A) A map of the existing and proposed boundaries;
B) A description of the existing uses and proposed future uses of:
i) The geographic area which is the subject of the proposed revision, and
ii) The areas adjacent to the geographic area in i).
3) An assessment, with supporting factual information, of the environmental impacts which may result from the proposed revision, including existing and proposed wasteloads and facilities to collect, transport and treat such wasteloads;
4) An assessment of the present worth analysis of alternatives to the proposed revision, including on-site and off-site treatment where applicable;
5) If available, written evidence of concurrence or objection by other agencies or by other persons who may be affected by the proposed revision;
6) Other information requested by the Agency.
b) The Agency will consider a petition complete when all relevant information set forth in this section has been provided.