Ill. Admin. Code tit. 35, § 730.189
1) There is no significant leak in the casing, tubing, or packer; and
1) The injection pressure, rate, and injected volumes;
e) The Agency must require any requested alternative test that the Agency has determined is necessary to evaluate mechanical integrity under subsections (a)(1) or (a)(2) after obtaining the written approval of USEPA.
BOARD NOTE: Corresponding 40 CFR 146.89(e) provides that the Agency must submit a written request to USEPA setting forth the proposed test and all technical data supporting its use to obtain approval for a new mechanical integrity test. USEPA stated that it will approve the request if USEPA determines that the proposed test will reliably demonstrate the mechanical integrity of wells for which its use was proposed. USEPA stated that it will publish any alternative method that USEPA has approved in the Federal Register, and the Agency must approve use of the published method if the Agency has determined that the method is appropriate to evaluate mechanical integrity, unless USEPA restricts its use at the time of approval by USEPA.
g) The Agency must require additional or alternative tests if the Agency determines that the results presented by the owner or operator pursuant to subsections (a) through (d) are not satisfactory to demonstrate that there is no significant leak in the casing, tubing, or packer or that there is no significant movement of fluid into a USDW resulting from the injection activity, as required by subsections (a)(1) and (a)(2).
BOARD NOTE: This Section corresponds with 40 CFR 146.89 (2017).
(Source: Amended at 42 Ill. Reg. 24145, effective November 19, 2018)