Ill. Admin. Code tit. 35, § 845.670
c) The corrective action plan must meet the following requirements:
d) The selected remedy in the corrective action plan must:
1) Be protective of human health and the environment;
e) Corrective Action Alternatives Analysis. In selecting a remedy that meets the standards of subsection (d), the owner or operator of the CCR surface impoundment must consider the following evaluation factors:
A) Magnitude of reduction of existing risks;
H) Potential need for replacement of the remedy.
2) The effectiveness of the remedy in controlling the source to reduce further releases based on consideration of each of the following potential factors:
B) The extent to which treatment technologies may be used.
B) Expected operational reliability of the technologies;
D) Availability of necessary equipment and specialists; and
f) The owner or operator must specify, as part of the corrective action plan, a schedule for implementing of, and completing, remedial activities. The schedule must require the completion of remedial activities within a reasonable time, taking into consideration the factors in this subsection (f). The owner or operator of the CCR surface impoundment must consider the following factors in determining the schedule of remedial activities:
5) Resource value of the aquifer, including:
C) Groundwater quantity and quality;