- a) A State or NPDES permit must include a plan for surface drainage control as a condition.
- b) The applicant's plan for surface drainage control must be incorporated into a permit by reference if it meets the standard of Section 405.102(a); otherwise, the Agency must deny the permit or issue it with a modified plan.
- c) Mining activities and depositing mine refuse must be planned and conducted so as to avoid contact or interference with waters of the State that could reasonably cause water pollution.
- d) Stream diversion, redirection or impoundment must not be undertaken when the Agency demonstrates that there is an economically reasonable alternative.
(Source: Amended at 43 Ill. Reg. 11606, effective September 25, 2019)