(1) No public utility that purchases, acquires, combines with, or merges with another public utility shall fail to honor an agreement entered into between the predecessor utility and a developer, property owner, or public utility customer unless:
- (a) The agreement has expired;
- (b) More than five (5) years has passed since the purchase, acquisition, combination, or merger; or
- (c) The parties mutually agree to change or terminate the agreement.
- (2) The commission is authorized to investigate and resolve complaints under this section pursuant to section 61-503, Idaho Code. The commission shall take action on such a complaint within forty-five (45) days after receipt.
[61-313A, added 2024, ch. 45, sec. 1, p. 252.]