- (1) All matters arising under this chapter shall be governed by the commission’s rules of procedure.
- (2) The commission’s proceeding to review an application for a route certificate for the construction of transmission facilities in a designated national interest electric transmission corridor shall constitute a necessary administrative remedy for a person aggrieved by a local government’s final land use action on a transmitting utility’s application to construct transmission facilities in a designated national interest electric transmission corridor. Judicial review shall not be available from a local government’s final land use decision concerning a transmitting utility’s application to construct transmission facilities in a national interest electric transmission corridor. A person aggrieved by a local government’s final land use action involving the construction of a proposed transmission facility route in a national interest electric transmission corridor must participate in the commission’s proceeding and seek judicial review of the commission’s final order.
- (3) Reconsideration of, appeal from, and stay of orders issued pursuant to this chapter shall be governed by law as for orders of the commission in other matters.
[61-1709, added 2007, ch. 186, sec. 1, p. 543.]