Haw. Rev. Stat. § 103D-501
(a) The policy board shall adopt rules requiring the inclusion of contract clauses providing for adjustments in prices, time of performance, or other contract provisions, as appropriate, and covering the following subjects:
(1) The unilateral right of the governmental body to order in writing:
(4) Site conditions differing from those indicated in the contract, or ordinarily encountered, except that differing site conditions clauses established by these rules need not be included in a contract:
(b) Adjustments in price permitted by rules adopted under subsection (a) shall be computed in one or more of the following ways:
(5) In the absence of agreement by the parties:
(B) For change orders with value exceeding $50,000 by a unilateral determination by the governmental body of the costs attributable to the events or situations under clauses with adjustment of profit or fee, all as computed by the governmental body in accordance with applicable sections of the rules adopted under section 103D-601 and subject to the provisions of part VII. When a unilateral determination has been made, a unilateral change order shall be issued within ten days. Costs included in the unilateral change order shall allow for twenty per cent of the actual costs for overhead and profit on work done directly by the contractor and ten per cent on any subcontractor's billing to the contractor for the contractor's overhead and profit. Upon receipt of the unilateral change order, if the contractor does not agree with any of the terms or conditions, or the adjustment or nonadjustment of the contract time or contract price, the contractor shall file a notice of intent to claim within thirty days after the receipt of the written unilateral change order. Failure to file a protest within the time specified shall constitute agreement on the part of the contractor with the terms, conditions, amounts, and adjustment or nonadjustment of the contract time or the contract price set forth in the unilateral change order.
A contractor shall be required to submit cost or pricing data if any adjustment in contract price is subject to the provisions of section 103D-312. A fully executed change order or other document permitting billing for the adjustment in price under any method listed in paragraphs (1) through (4) shall be issued within ten days after agreement on the method of adjustment.
(c) The policy board shall adopt rules requiring the inclusion in contracts of clauses providing for appropriate remedies and covering the following subjects:
(d) The chief procurement officer or the head of a purchasing agency may vary the clauses that may be required to be included in contracts under the rules adopted under subsections (a) and (c); provided that:
[L Sp 1993, c 8, pt of §2; am L 1997, c 352, §23; am L 2000, c 164, §3; am L 2006, c 291, §4]