Fla. Stat. § 1013.64
Allocations from the Public Education Capital Outlay and Debt Service Trust Fund to the various boards for capital outlay projects shall be determined as follows:
(g) When an existing educational plant is determined to be unsatisfactory pursuant to the survey conducted under s. 1013.31, the board may, by resolution, designate the plant as a historic educational facility and may use funds generated for renovation and remodeling pursuant to this section to restore the facility for use by the board. The board shall agree to pay renovation and remodeling costs in excess of funds which such facility would have generated through the depreciation formula in paragraph (a) had the facility been determined to be satisfactory. The board shall further agree that the plant shall continue to house students. The board may designate a plant as a historic educational facility only if the Division of Historical Resources of the Department of State or the appropriate historic preservation board under chapter 266 certifies that:
1. The plant is listed or determined eligible for listing in the National Register of Historic Places pursuant to the National Historic Preservation Act of 1966, as amended, 16 U.S.C. s. 470;
2. The plant is designated historic within a certified local district pursuant to s. 48(g)(3)(B)(ii) of the Internal Revenue Code; or
3. The division or historic preservation board otherwise finds that the plant is historically significant.
(2) (a) The department shall establish, as a part of the Public Education Capital Outlay and Debt Service Trust Fund, a separate account, in an amount determined by the Legislature, to be known as the "Special Facility Construction Account." The Special Facility Construction Account shall be used to provide necessary construction funds to school districts which have urgent construction needs but which lack sufficient resources at present, and cannot reasonably anticipate sufficient resources within the period of the next 3 years, for these purposes from currently authorized sources of capital outlay revenue. A school district requesting funding from the Special Facility Construction Account shall submit one specific construction project, not to exceed one complete educational plant, to the Special Facility Construction Committee. No district shall receive funding for more than one approved project in any 3-year period. The first year of the 3-year period shall be the first year a district receives an appropriation. The department shall encourage a construction program that reduces the average size of schools in the district. The request must meet the following criteria to be considered by the committee:
1. The project must be deemed a critical need and must be recommended for funding by the Special Facility Construction Committee. Prior to developing plans for the proposed facility, the district school board must request a preapplication review by the Special Facility Construction Committee or a project review subcommittee convened by the committee to include two representatives of the department and two staff from school districts not eligible to participate in the program. Within 60 days after receiving the preapplication review request, the committee or subcommittee must meet in the school district to review the project proposal and existing facilities. To determine whether the proposed project is a critical need, the committee or subcommittee shall consider, at a minimum, the capacity of all existing facilities within the district as determined by the Florida Inventory of School Houses; the district's pattern of student growth; the district's existing and projected capital outlay full-time equivalent student enrollment as determined by the department; the district's existing satisfactory student stations; the use of all existing district property and facilities; grade level configurations; and any other information that may affect the need for the proposed project.
2. The construction project must be recommended in the most recent survey or surveys by the district under the rules of the State Board of Education.
3. The construction project must appear on the district's approved project priority list under the rules of the State Board of Education.
4. The district must have selected and had approved a site for the construction project in compliance with s. 1013.36 and the rules of the State Board of Education.
5. The district shall have developed a district school board adopted list of facilities that do not exceed the norm for net square feet occupancy requirements under the State Requirements for Educational Facilities, using all possible programmatic combinations for multiple use of space to obtain maximum daily use of all spaces within the facility under consideration.
6. Upon construction, the total cost per student station, including change orders, must not exceed the cost per student station as provided in subsection (6).
7. There shall be an agreement signed by the district school board stating that it will advertise for bids within 30 days of receipt of its encumbrance authorization from the department.
8. The district shall, at the time of the request and for a continuing period of 3 years, levy the maximum millage against their nonexempt assessed property value as allowed in s. 1011.71(2) or shall raise an equivalent amount of revenue from the school capital outlay surtax authorized under s. 212.055(6). Any district with a new or active project, funded under the provisions of this subsection, shall be required to budget no more than the value of 1.5 mills per year to the project to satisfy the annual participation requirement in the Special Facility Construction Account.
9. If a contract has not been signed 90 days after the advertising of bids, the funding for the specific project shall revert to the Special Facility New Construction Account to be reallocated to other projects on the list. However, an additional 90 days may be granted by the commissioner.
10. The department shall certify the inability of the district to fund the survey-recommended project over a continuous 3-year period using projected capital outlay revenue derived from s. 9(d), Art. XII of the State Constitution, as amended, paragraph (3)(a) of this section, and s. 1011.71(2).
11. The district shall have on file with the department an adopted resolution acknowledging its 3-year commitment of all unencumbered and future revenue acquired from s. 9(d), Art. XII of the State Constitution, as amended, paragraph (3)(a) of this section, and s. 1011.71(2).
12. Final phase III plans must be certified by the board as complete and in compliance with the building and life safety codes prior to August 1.
(3) (a) Each district school board shall receive an amount from the Public Education Capital Outlay and Debt Service Trust Fund to be calculated by computing the capital outlay full-time equivalent membership as determined by the department. Such membership must include, but is not limited to:
1. K-12 students, except hospital and homebound part-time students; and
2. Students who are career and technical education students, and adult disabled students and who are enrolled in school district technical centers. The capital outlay full-time equivalent membership shall be determined for kindergarten through the 12th grade and for technical centers by averaging the unweighted full-time equivalent student membership for the second and third surveys and comparing the results on a school-by-school basis with the Florida Inventory for School Houses. The capital outlay full-time equivalent membership by grade level organization shall be used in making the following calculations: The capital outlay full-time equivalent membership by grade level organization for the 4th prior year must be used to compute the base-year allocation. The capital outlay full-time equivalent membership by grade-level organization for the prior year must be used to compute the growth over the highest of the 3 years preceding the prior year. From the total amount appropriated by the Legislature pursuant to this subsection, 40 percent shall be allocated among the base capital outlay full-time equivalent membership and 60 percent among the growth capital outlay full-time equivalent membership. The allocation within each of these groups shall be prorated to the districts based upon each district's percentage of base and growth capital outlay full-time membership. The most recent 4-year capital outlay full-time equivalent membership data shall be used in each subsequent year's calculation for the allocation of funds pursuant to this subsection. If a change, correction, or recomputation of data during any year results in a reduction or increase of the calculated amount previously allocated to a district, the allocation to that district shall be adjusted correspondingly. If such recomputation results in an increase or decrease of the calculated amount, such additional or reduced amounts shall be added to or reduced from the district's future appropriations. However, no change, correction, or recomputation of data shall be made subsequent to 2 years following the initial annual allocation.
(5) District school boards shall identify each fund source and the use of each proportionate to the project cost, as identified in the bid document, to assure compliance with this section. The data shall be submitted to the department, which shall track this information as submitted by the boards. PECO funds shall not be expended as indicated in the following:
(b) 1. A district school board must not use funds from the Public Education Capital Outlay and Debt Service Trust Fund or the School District and Community College District Capital Outlay and Debt Service Trust Fund for any new construction of educational plant space with a total cost per student station, including change orders, that equals more than:
a. $11,600 for an elementary school,
b. $13,300 for a middle school, or
c. $17,600 for a high school, (1997) as adjusted annually by the Consumer Price Index.
2. A district school board must not use funds from the Public Education Capital Outlay and Debt Service Trust Fund or the School District and Community College District Capital Outlay and Debt Service Trust Fund for any new construction of an ancillary plant that exceeds 70 percent of the average cost per square foot of new construction for all schools.
History.--s. 861, ch. 2002-387.