Fla. Stat. § 715.12
(3) The terms used in this section have the same definitions as the terms defined in s. 713.01. As used in this section, the term:
(4) An obligor must pay an obligee with whom the obligor has a contract when all of the following events have occurred:
(7) (a) An owner and a contractor may agree to a provision that allows the owner to withhold a portion of each progress payment until substantial completion of the entire project. The owner shall pay the contractor the balance of the contract price, including the amounts withheld from the progress payments, within 14 days after any of the following events occur.
1. Pursuant to the terms of the contract, an architect or engineer certifies that the project is substantially complete and, within the time provided in the contract between the owner and the contractor, the owner submits a written punchlist to the contractor and the contractor substantially completes all of the items on the punchlist.
2. The issuance of a certificate of occupancy for the project, and within the time provided in the contract between the owner and the contractor, the owner submits a written punchlist to the contractor and the contractor substantially completes all of the items on the punchlist.
3. The owner or a tenant of the owner takes possession of the construction project and, within the time provided in the contract between the owner and the contractor, the owner submits a written punchlist to the contractor and the contractor substantially completes all of the items on the punchlist. Any funds retained by the owner beyond the time period specified in this subsection shall accrue interest at the rate specified in subsection (5), computed from the date the payment is due to the date the payment is received by the contractor. If the contract between the owner and the contractor does not provide a time period for the owner to submit a written punchlist to the contractor, the time period shall be 15 days from the issuance of the certificate of substantial completion, the issuance of the certificate of occupancy, or the date the owner or the owner's tenant takes possession of the project, whichever first occurs. If no written punchlist is given to the contractor within the time provided in this subsection, interest begins to accrue 14 days after the issuance of the certificate of substantial completion, the issuance of the certificate of occupancy, or the date the owner or the owner's tenant takes possession of the project, whichever first occurs. For construction projects that are to be built in phases, this subsection applies to each phase of the total project. The contract between the owner and the contractor may specify a shorter time period for disbursing all or any portion of the final payment and the retainage.
(c) An obligee may, from time to time, withdraw all or any portion of the amount retained from progress payments upon depositing with the obligor:
1. United States Treasury bonds, United States Treasury notes, United States Treasury certificates of indebtedness, or United States Treasury bills;
2. Bonds or notes of the State of Florida; or
3. Certificates of deposit, within the insured limits, from a state or national bank or state or federal savings and loan association authorized to do business in this state. Amounts may not be withdrawn in excess of the market value of the securities listed in subparagraphs 1., 2., and 3. at the time of such withdrawal or in excess of the par value of such securities, whichever is less. The obligee shall execute and deliver all documents reasonably required to allow the obligor to document the transfer and the obligee shall pay any recording or registration costs incurred by the obligor in connection with the transfer. The obligor shall pay the obligee any interest or income earned on the securities so deposited within 30 days after the date such interest or income is received by the obligor. If the deposit is in the form of coupon bonds, the obligor shall deliver each coupon to the obligee within 30 days after the date the coupon matures. An obligee may withdraw funds retained from progress payments only to the extent the obligor has withdrawn such funds for the obligee's labor, services, or materials from the person immediately above the obligor in the chain of contracts.
History.--s. 1, ch. 92-286; s. 32, ch. 93-166.