(3) This general permit is subject to the following conditions:
(h) Cultural Resources and/or Historic Properties. In addition to the conditions for general permits in Rule 62-331.200, F.A.C., the following shall apply:
1. No structure or work shall adversely affect, impact, or disturb properties listed in the National Register of Historic Places (NRHP), or those eligible for listing in the NRHP where the adverse effect, impact, or disturbance has not been resolved through consultation with the SHPO.
2. The applicant shall determine and document, in consultation with SHPO, the scope of identification efforts for cultural resources within the undertaking’s area of potential effect and establish a determination of effects based upon these efforts. Documentation of this scope of identification efforts and determination shall be provided in summary form to the Agency along with the concurrence documents from SHPO.
3. If an archaeological monitor is required. A professional archeologist who meets the “Archeology and Historic Preservation: Secretary of Interior’s Standards and Guidelines” shall be onsite during the initial ground-disturbing activities. The professional archeologist shall be responsible for monitoring the spoil and ground disturbance for archaeological deposits. Should potential significant archaeological deposits (which shall include, but not be limited to: pottery, modified shell, flora, fauna, human remains, ceramics, stone tools or metal implements, dugout canoes, evidence of structures or any other physical remains that could be associated with Native American cultures or early colonial or American settlement), recovery be encountered, all work and ground disturbing activities must cease within a 100-meter diameter of the discovery to allow for proper assessment, recording, and recovery of the cultural deposits in a professional manner. The archeologist on site shall notify the Permittee, SHPO, and the Agency the same business day to assess the significance of the discovery and devise appropriate actions, including salvage operations, coordination with the SHPO/THPO, Tribes, and other consulting parties, as appropriate and in compliance with applicable historic preservation laws. Upon completion of the monitoring activities, an archaeological letter must be submitted to the Director of Florida’s Division of Historical Resources (who also serves as the SHPO), along with an updated Florida Master Site File form and, as appropriate, a monitoring report.
(i) Compensatory Mitigation.
1. Mitigation may be accomplished by one or more of the following mechanisms and preference hierarchy.
a. Securing appropriate number and resource type of credits from approved mitigation bank within the project’s service area;
b. Payment of mitigation fees to an approved in-lieu program within the project’s service area;
c. Through a “permittee-responsible” mitigation, including those mitigation projects that are part of the FDOT Mitigation Program in Section 373.4137, F.S.; on-site and in-kind mitigation; or off-site or out-of-kind compensatory mitigation.
d. It is the responsibility of the applicant to demonstrate to the Agency that the mitigation proposal is the environmentally preferable option to replace the ecological functions and services that would be lost though the implementation of any work proposed. All mitigation proposals must be approved prior to verification of this general permit.
2. Prior to proceeding with the activity authorized in this general permit, a final mitigation plan must be approved by the Agency. If the approved mitigation plan is the purchase of mitigation bank or in lieu fee credits, the credits must be purchased or in-lieu fees paid prior to proceeding.
3. When the purchase of mitigation credits is applicable, the Permittee shall provide verification to the Agency indicating the number and type of credits purchased and the specific federal mitigation bank from which credits have been purchased. When payment of in-lieu fees is applicable, evidence of fee payment shall be provided to the Agency. The above-described verification or notification shall be provided to the Agency before commencement of the activities authorized by this general permit.
4. If the general permit verification includes permittee-responsible mitigation, the mitigation plan shall address the components of a complete mitigation plan as described in Rule 62-331.130, F.A.C.
(u) As-Built Certification. Within 60 days of completion of the work authorized by this permit, the Permittee shall submit to the Agency as-built drawings of the authorized work and a completed Form 62-331.248(1) “As-Built Certification By Professional Engineer”, incorporated by reference herein ( HYPERLINK "https://www.flrules.org/Gateway/reference.asp?No=Ref-12077" https://www.flrules.org/Gateway/reference.asp?No=Ref-12077). The as-built drawings shall be signed and sealed by a registered professional engineer and include the following:
1. A plan view drawing of the location of the authorized work footprint, as shown on the permit drawings, with transparent overlay of the work as constructed in the same scale as the permit drawings on 8½-inch by 11-inch sheets. The plan view drawing should show all “earth disturbance,” including wetland impacts and water management structures.
2. A list of any deviations between the work authorized by this permit and the work as constructed. In the event that the completed work deviates, in any manner, from the authorized work, describe on the attached “As-Built Certification By Professional Engineer” form the deviations between the work authorized by this permit and the work as constructed. Clearly indicate on the as-built drawings any deviations that have been listed. Please note that the depiction and/or description of any deviations on the drawings and/or “As-Built Certification By Professional Engineer” form does not constitute approval of any deviations by the Agency.
3. Include the permit number on all sheets submitted.
Editor notes: The effective date of the rule will be the effective date of assumption, which is the date identified by EPA as published in the Federal Register §373.4146, F.S.
Rulemaking Authority 373.026(7), 373.043, 373.118(1), 373.4131, 373.414(9), 373.4145, 373.4146(2), 403.805(1) FS. Law Implemented 373.118, 373.129, 373.136, 373.413, 373.4131, 373.414, 373.4145, 373.4146, 373.416, 373.422, 373.423, 373.429 FS. History–New 12-22-20.