Fla. Admin. Code R. 59A-4.134
(2) Approval to start construction only for demolition, site work, foundation, and building structural frame may be obtained prior to construction document approval when the following is submitted for review and approval:
(3) Projects that have been submitted to the Agency for review will be considered abandoned and will be terminated after any of the following has occurred:
(7) Plans and specifications may be submitted in three stages of development described in this rule. Approval of a Stage III submission is required to begin construction (except as permitted by subsection 59A-4.134(2), F.A.C.). These stages are as follows:
(9) For projects involving only equipment changes or system renovations, construction documents need to be submitted. These documents must include the following:
(10) Stage I, Schematic Plans – The following must be incorporated into the schematic plans:
(11) Stage II, Preliminary Plans – Stage II preliminary plans will be approved by the Agency upon successful demonstration that the construction will comply with applicable life safety code requirements, flood requirements and that the layout will accommodate all required functional space as evidenced by a thorough examination of the documents submitted as required by this subsection. Stage II preliminary plans must include:
(b) Site development plans that:
1. Show existing grades and proposed improvement as required by the schematic submission.
2. Provide building locating dimensions.
3. Provide site elevations for both the 100 year flood elevations and hurricane category 3 surge inundation elevations if the project involves the construction of a new facility or is a new addition of a wing or floor to an existing facility.
4. Provide the location of the fire protection services water source to the building.
(c) Architectural plan that include:
1. Floor plans, 1/8-inch scale minimum, showing door swings, windows, casework and millwork, fixed equipment and plumbing fixtures. Indicate the function of each space.
2. A large-scale plan of typical new bedrooms with tabulation of gross and net square footage of each bedroom. Tabulate the size of the bedroom window glass.
3. Typical large-scale interior and exterior wall sections to include typical rated fire and fire/smoke partitions and a typical corridor partition.
4. All exterior building elevations.
5. Equipment that is not included in the construction contract but that requires mechanical or electrical service connections or construction modifications must be identified to assure its coordination with the architectural, mechanical and electrical phases of construction.
6. If the project is located in an occupied facility, preliminary phasing plans indicating how the project is to be separated from all occupied areas.
(d) Life safety plans that include:
1. Single-sheet floor plans showing fire and smoke compartmentation, all means of egress and all exit signs. Additionally, depict and provide the dimension for the longest path of travel in each smoke compartment to the door(s) to the adjoining compartment, calculate the total area of the smoke compartment in square feet, and tabulate exit inches.
2. All sprinklered areas, fire extinguishers, fire alarm devices and pull station locations.
3. Fully developed life safety plans, if the project is an addition or conversion of an existing building.
4. Life safety plans of the floor being renovated and required exit egress floor(s) if the project is a renovation in an existing building.
5. When demolition or construction is to be undertaken in and around occupied buildings, a life safety plan indicating temporary egress and detailed phasing plans indicating how the areas to be demolished or constructed are to be separated from all occupied areas.
(e) Mechanical engineering plans that include:
1. Single-sheet floor plans with a one-line diagram of the ventilating system with relative pressures of each space. Provide a written description and drawings of the anticipated smoke control system, passive or active, and a sequence of operation correlated with the life safety plans.
2. The general location of all fire and smoke dampers, all duct smoke detectors and fire stats.
3. If the building is equipped with fire sprinklers, the location of the sprinkler system risers and the point of connection for the fire sprinkler system. State the method of design for the existing and new fire sprinkler systems.
4. The locations of all plumbing fixtures and other items of equipment requiring plumbing services and/or gas service.
5. The locations of any fume, radiological or chemical hoods.
6. The locations of all medical gas outlets, piping distribution risers, terminals, alarm panels, low pressure emergency oxygen connection, isolation/zone valves, and gas source locations.
7. The locations and relative size of major items of mechanical equipment such as chillers, air handling units, fire pumps, medical gas storage, boilers, vacuum pumps, air compressors and fuel storage vessels.
8. The locations of hazardous areas and the volume of products to be contained therein.
9. The location of fire pump, stand pipes, and sprinkler risers.
(f) Electrical engineering drawings that include:
1. A one-line diagram of normal and essential electrical power systems showing service transformers and entrances, switchboards, transfer switches, distribution feeders and over-current devices, panel boards and step-down transformers. The diagram must include a preliminary listing and description of new and existing, normal and emergency loads, preliminary estimates of available short-circuit current at all new equipment and existing equipment serving any new equipment, short-circuit and withstand ratings of existing equipment serving new loads and any new or revised grounding requirements.
2. Fire alarm zones and correlate with the life safety plan.
(12) Stage III, Construction Documents – The Stage III construction documents shall be an extension of the Stage II preliminary plan submission and shall provide a complete description of the contemplated construction. Stage III construction documents will be approved by the Agency upon successful demonstration that the construction will comply with all applicable codes and standards as evidenced by a thorough examination of the documents submitted as required by this subsection. Construction documents shall be signed, sealed, dated and submitted for written approval to the Agency’s Office of Plans and Construction submitted by a Florida registered architect and Florida registered professional engineer. An architecture or engineering firm, not practicing as a sole proprietor, must provide proof of registration as an architecture or engineering firm with the Florida Department of Business and Professional Regulation. The documents must consist of work related to civil, structural, mechanical, and electrical engineering, fire protection, lightning protection, landscape architecture and all architectural work. In addition to the requirements for Stage II submission, the following must be incorporated into the construction documents:
(c) Architectural plans.
1. Typical large-scale details of all typical interior and exterior walls and smoke walls, horizontal exist and exit passageways.
2. Comprehensive ceiling plans that show all utilities, lighting fixtures, smoke detectors, ventilation devices, sprinkler head locations and fire-rated ceiling suspension member locations where applicable.
3. Floor/ceiling and roof/ceiling assembly descriptions for all conditions.
4. Details and other instructions to the contract on the construction documents describing the techniques to be used to seal floor construction penetrations to the extent necessary to prevent smoke migration from floor to floor during a fire.
(i) A complete set of specifications of all work to be undertaken.
1. All project required contractor supplied testing and/or certification reports must be submitted in type written format, on standard forms, reviewed and accepted by the Engineer of Record prior to presenting to the Agency for review.
2. The specifications must require a performance verification test and balance air quality value report for two operating conditions for each air handling unit system. One operating condition must be with the specified air filters installed in the minimum pressure drop or clean state. The second operating condition must be at the maximum pressure drop and/or dirty state. The air quantities reported are acceptable if they are within ten percent of the design value and the space relative pressures are maintained. This requirement applies to any air-handling unit affected by the construction to be performed.
Rulemaking Authority 400.23 FS. Law Implemented 400.141, 400.232 FS. History–New 12-21-15.