Del. Code Ann. tit. 12, § 1166
(b) The State Escheator shall allow or deny the claim and give the claimant notice of the determination in a written record, which includes the State Escheator’s initial attempt to pay or deliver the property to the claimant. If the claim is denied, the State Escheator shall inform the claimant of the reason for the denial and specify what additional evidence, if any, is required for the claim to be reconsidered.
(d) (1) For any property paid or delivered to the State Escheator before August 1, 2022, or for any property paid or delivered to the State Escheator from a bankruptcy proceeding, where the State Escheator subsequently determines that the holder’s payment or delivery of property is less than the amount reported by the holder, the State Escheator shall pay any claim allowed on a pro rata basis determined by dividing the amount of property paid or delivered by the amount of property reported.
81 Del. Laws, c. 1, § 2; 83 Del. Laws, c. 59, § 10; 83 Del. Laws, c. 346, § 6