D.C. Mun. Regs. tit. 8-B, § 3316
3316.1 If the Director of Procurement (the "Director") has determined that an invitation for bids ("IFB") issued under chapter 32 will be canceled and that use of negotiation is appropriate to complete the procurement, the contracting officer may award a contract after using negotiation procedures without issuing a new solicitation if all of the following conditions are met:
3316.2 If an IFB has been canceled in accordance with §§3230.4(g) or 3230.4(h) of chapter 32, and the Director has authorized procurement through negotiation, the contracting officer shall proceed with the procurement in accordance with the provisions of this chapter, or the sole source provisions of chapter 34 of this title, if applicable.
SOURCE: Final Rulemaking published at 39 DCR 2566 (April 10, 1992).