D.C. Mun. Regs. tit. 27, § 4714
4714.1 Within the contract types described in sections 4711 through 4713, the Department may adopt a number of project delivery methods, including those set forth in subsection 4701.1 as may be in District's best interest.
4714.2 As part of the procurement planning process, the Director or Deputy Director, pursuant to a delegation from the Director to make such determinations, will determine the most appropriate delivery method for the project based on, among other considerations:
4714.3 The general types of delivery methods include:
the Department conducts the project in a manner similar to the Construction Manager at Risk approach. However, in the Construction Manager with Design Assist approach, a portion of the design work — typically the mechanical, electrical, and plumbing systems — is managed by the contractor;
(d) Design-Build: Under this approach, the Department retains a single entity to be responsible for the design and construction activities. Work under the Design-Build approach is typically divided into two (2) phases: preconstruction and construction. The contractor is required to bid its fees upfront and all of the major trade packages must be competitively bid as well;
(e) Modified Design-Build: Under this approach, the Department uses a bridging methodology where it will engage an architect during the early stages of the project (referred to as design development) and then assign the architect's contract to the contractor at the appropriate stage of the project. The remainder of the project then proceeds under the Design-Build approach;
(f) Design-Build-Finance-Operate-Maintain: Under this approach, the Department retains a single entity to be responsible for the design and construction activities. Work under the Design-Build approach is typically divided into two (2) phases: preconstruction and construction. The contractor is required to bid its fees upfront and all of the major trade packages must be competitively bid as well. In addition, the contractor would be responsible for operating and maintaining the facility. Payment for design and construction services would be paid out over a negotiated term; and
(g) Design-Build-Operate-Maintain: Under this approach, the Department retains a single entity to be responsible for the design and construction activities. Work under the Design-Build approach is typically divided into two (2) phases: preconstruction and construction. The contractor is required to bid its fees upfront and all of the major trade packages must be competitively bid as well. In addition, the contractor would be responsible for operating and maintaining the facility.
4714.4 The Department may combine aspects of the methods listed in subsection 4714.3 or alter aspects of these methods if doing so is in the best interest of the District.
4714.5 Contractors, including architects, construction managers, and design builders, required to facilitate these delivery methods shall be selected in accordance with the contracting procedures in sections 4717 through 4722.
10, 2012).