D.C. Mun. Regs. tit. 21, § 5347
Claims Filed with the General Manager
Authority: Water and Sewer Authority Establishment and Department of Public Works Reorganization Act of 1996, effective April 18, 1996, as amended (D.C. Law 11-111, §§ 203(3), (5), and (6) and 205(a)(3) and (7); D.C. Code §§ 34-2202.03(3), (5), and (6) and 34-2202.05(a)(3) and (7)), and Board Resolution # 09-74 Source: Emergency Rulemaking published at 46 DCR 613 (January 22, 1999) [EXPIRED]; as Final Rulemaking published at 46 DCR 7349 (September 17, 1999); as amended by Final Rulemaking published at 56 DCR 4484 (June 12, 2009).District of Columbia, Office of the Secretary
5347.1 If a contractor's claim against WASA is not resolved to the satisfaction of the contractor under Sections 5346 or 5352, the contractor may file the claim with the General Manager:
- (a) Within thirty (30) calendar days after the receipt of the Contracting Officer's written decision; or
- (b) Ten (10) calendar days after the expiration of the time for a decision by the Contracting Officer under Section 5346.
5347.2 The contractor's claim shall be in writing, shall be delivered in person or mailed by certified mail, return receipt requested, to the General Manager, and shall contain at least the following:
- (a) A description of the claim and the amount in dispute;
- (b) Any data or other information in support of the claim;
- (c) A copy of the Contracting Officer's written decision or a statement that no written decision was received; and
- (d) The contractor's request for relief.
SOURCE: Emergency Rulemaking published at 46 DCR 613 (January 22, 1999) [EXPIRED]; as Final Rulemaking published at 46 DCR 7349 (September 17, 1999).