D.C. Mun. Regs. tit. 21, § 5341
Project Delivery Methods
Effective Jun 12, 200956 DCR 4484Authority: Water and Sewer Authority Establishment and Department of Public Works Reorganization Act of 1996, effective April 18, 1996, as amended (D.C. Law 11-111, §§ 203(3), (5), and (6) and 205(a)(3) and (7); D.C. Code §§ 34-2202.03(3), (5), and (6) and 34-2202.05(a)(3) and (7)), and Board Resolution # 09-74 Source: Emergency Rulemaking published at 46 DCR 613 (January 22, 1999) [EXPIRED]; as Final Rulemaking published at 46 DCR 7349 (September 17, 1999); as amended by Final Rulemaking published at 56 DCR 4484 (June 12, 2009).District of Columbia, Office of the Secretary
5341.1 The Authority may select and employ a project delivery method determined to be appropriate to the specific contract and to serve the Authority's interests.
SOURCE: Emergency Rulemaking published at 46 DCR 613 (January 22, 1999) [EXPIRED]; as Final Rulemaking published at 46 DCR 7349 (September 17, 1999); as amended by Final Rulemaking published at 56 DCR 4484 (June 12, 2009).