Conn. Agencies Regs. § 13b-283-5
(1) The State shall pay seventy percent (70%) of all project costs. The municipality in which the orphan bridge is located shall pay fifteen percent (15%) of all project costs. The railroad over which an orphan bridge passes shall pay fifteen percent (15%) of all project costs, except on those projects where a federal aid funding is used, the Railroad's share shall be in accordance with federal law. In the case where more than one railroad company owns track beneath an orphan bridge, the cost shall be divided equally between such railroad companies.
For those portions of the project costs that the municipality and the railroad are legally obligated to pay, there shall be no restrictions on the source of these funds and may include funds made available through other Federal or State grant or loan programs, as those programs allow.
(Effective June 27, 1986)