7 C.F.R. § 1924.13
This section includes additional provisions that apply to planning and conduct of construction work on all multiple family housing projects and other projects that are more extensive in scope and more complex in nature than individual housing units or farm buildings. This section will apply in addition to all other requirements contained elsewhere in this subpart.
(a) Architectural services. Complete architectural services, as defined in § 1924.4(o)(1) of this subpart are recommended on all projects. They are required for projects involving an LH grant and for all loans for RRH, RCH, and LH projects consisting of more than 4 units unless prior consent to making an exception to the requirements for complete architectural services is obtained from the National Office. If the applicant or contractor is an architect or organization with architectural capability, the applicant must, nevertheless, hire an independent qualified architect or architectural firm to inspect the construction work and perform other needed services during the construction and warranty phases. See Guide 4, attachment 1, “Attachment to AIA Document—Standard Form of Agreement Between Owner and Architect,” for further information (available in any Agency office).
(4) Agreement between borrower and architect. The borrower and the architect will execute a written agreement. The agreement must provide:
(iii) That the agreement and any amendments to the agreement shall not be in full force and effect until concurred with in writing by the State Director or the State Director's delegate, and it will contain the following provision:
The Agency, as potential lender or insurer of funds to defray the costs of this agreement and without liability for any payments thereunder, hereby concurs in the form, content and the execution of this agreement. Date Agency Approval Official Title
(5) Specific services. Architectural services will include six consecutive phases as follows:
(i) Schematic design phase. The architect will:
(ii) Design development phase. The architect will:
(iii) Construction documents phase. The architect will:
(iv) Bidding or negotiation phase. The architect will, as appropriate, for a bidded or negotiated contract:
(v) Construction phase. This phase includes the administration of the construction contract. It will commence with the award of the construction contract and end when the borrower makes final payment to the contractor. The architect will:
(b) Other professional services. The State Director, on the recommendation of the State architect/engineer, may request that additional professional services be provided.
(2) When a project representative is utilized, unless otherwise agreed, the representative will be provided by the consulting architect/engineer. Prior to the preconstruction conference, the architect/engineer will submit a resume of qualifications of the project representative to the applicant and to the Agency for acceptance in writing. If the applicant provided the project representative, the applicant must submit a resume of the representative's qualifications to the project architect/engineer and the Agency for acceptance in writing, prior to the preconstruction conference. The project representative will attend the preconstruction conference where duties and responsibilities will be fully discussed. The project representative will work under the general supervision of the architect/engineer. The project representative will maintain a daily diary in accordance with the following:
(c) Drawings. The type and kinds of drawings should be in accordance with exhibit C of this subpart and subpart D of part 1944 of this chapter.
(e) Methods of administering construction. Projects involving a total development cost of less than $100,000 which do not include an LH grant may, with the approval of the State Director, follow the contract procedure in § 1924.6(a) of this subpart without modification. Construction of all other projects, however, will be administered by the contract method or owner-builder method as set forth in this section.
(1) Contract method. This method of development will be used for all complex construction except in cases where owner-builder method is authorized. Development under this method is done in accordance with § 1924.6(a) of this subpart except as modified by this paragraph. All construction work will be completed under one written construction contract. Guide 1, “Contract Documents,” of this subpart (available in any Agency office) is provided to assist Agency personnel and applicants in assembling and reviewing contract documents for more complex construction such as that administered under this section.
(i) Competitive bidding methods.
(D) If advertising does not provide a satisfactory bid in the opinion of the applicant and the Agency, the applicant shall reject all bids and will then be free to negotiate with bidders on anyone else to obtain a satisfactory contract. The following conditions must be met:
(1) The State Director determines that the original competitive bid process was handled in a satisfactory manner and that there is no advantage to advertising for competitive bid again.
(2) The requirements of paragraph (e)(1)(vii) of this section are met.
(ii) Contract documents. Contract documents will conform with recognized professional practices as prescribed in this paragraph. Such contract documents will contain substantially the following:
Item I Invitation for Bids (Form RD 1924-5) Item II Information for Bidders Item III Bid Item IV Bid Bond Item V Agreement (Construction Contract) Item VI Compliance Statement (Form RD 400-6) Item VII General Conditions Item VIII Supplemental General Conditions Item IX Payment Bond (exhibit F of this subpart) Item X Performance Bond (exhibit G of this subpart) Item XI Notice of Award Item XII Notice of Proceed Item XIII Drawings and Specifications Item XIV Addenda Item XV Contract Change Order (Form RD 1924-7) Item XVI Labor Standards Provisions [Where applicable] Item XVII Monthly Employment Utilization Report (Form CC-257) Item XVIII Partial Payment Estimate (Form RD 1924-18) Item XIX Builder's Warranty (Form RD 1924-19)
(H) All contracts will contain a provision that they are not in full force and effect until concurred with by the State Director or the State Director's delegate, in writing. Therefore, before loan closing or before the start of construction, whichever occurs first, the State Director or the State Director's delegate will concur in the contract form, content, and execution if acceptable, by including the following paragraph at the end of the contract:
The Agency, as potential lender or insurer of funds to defray to costs of this contract, and without liability for any payments thereunder, hereby concurs in the form, content, and execution of this contract. Date Agency Official Title
(iii) Surety. When multiple advances of loan or grant funds are utilized, surety that guarantees both payment and performance in the full amount of the contract will be provided in accordance with § 1924.6(a)(3)(ii) of this subpart. Exceptions to the surety requirements shall be governed by the following:
(B) For loans or grants to applicants other than non-profit organizations or public bodies that are within the State Director's approval authority, the State Director may, upon request of the borrower or grantee, grant exceptions to the surety requirements in accordance with the provisions of § 1924.6(a)(3)(iii) of this subpart. Before granting such an exception, however, the State Director should be provided the following information from the proposed contractor in order to fully evaluate the experience and capabilities of the contractor:
(1) A resume indicating the contractor's history, ability and experience.
(2) A current, dated and signed financial statement of the contractor's operations indicating the payment status of accounts and any contingent liabilities that may exist. Agency personnel will be responsible for analyzing the financial statement as to the sufficiency of the contractor's financial capability to carry out construction. The financial strength must demonstrate the ability of the contractor to pay all bills prior to receiving periodic draws of funds from the lender.
(3) A credit report (obtained at no expense to the Agency) attesting to the contractor's credit standing.
(4) A listing of trade references that could be contacted to substantiate the contractor's experience and good standing.
(5) Statements from owners for whom the contractor has done similar work, indicating the scope of the work and the owner's evaluation of the contractor's performance.
(C) For loans or grants to applicants other than non-profit organization or public bodies that are in excess of the State Director's approval authority, the State Director may request National Office authorization to grant one of the exceptions to the surety requirements as indicated in § 1924.6(a)(3)(iii) of this subpart. The following information must be submitted with the request to the National Office:
(1) An explanation of why interim financing is not available.
(2) An explanation of why the proposed contractor cannot obtain surety bonds meeting the requirements of § 1924.6(a)(3)(ii) of this subpart.
(3) The information listed in paragraph (e)(1)(iii)(B) of this section.
(4) The drawings and specifications for the proposed project, together with the comments of the State architect/engineer.
(5) The applicant's written request for an exception.
(6) An explanation of why the requirements of § 1924.6(a)(3)(iii) (A) or (B) of this subpart cannot be met in those cases where the State Director requests authorization to grant an exception as indicated in § 1924.6(a)(3)(iii)(C) of this subpart. When such a request is made, the documentation required of the contractor under the provision must also be forwarded.
(7) The State Director's recommendation.
(v) Cost certification. Whenever the State Director determines it appropriate, and in all situations where there is an identity of interest as defined in § 1924.4(i) of this subpart, the borrower, contractor and any subcontractor, material supplier, or equipment lessor having an identity of interest must each provide certification using Form RD 1924-13 as to the actual cost of the work performed in connection with the construction contract. The construction costs, as reported on Form RD 1924-13, must also be audited, in accordance with Government Auditing Standards, by a CPA, or LPA licensed on or before December 31, 1970. In addition, certain agreed upon procedures (available in any Agency office) will be performed in accordance with Attestation Standards. In some cases, the Agency will contract directly with a CPA or LPA for the cost certification. In that event, documentation necessary to have the costs of construction certified by an Agency contractor that they were the actual costs of the work performed, as reported on Form RD 1924-13, will be provided. Funds which were included in the loan for cost certification and which are ultimately not needed because Agency contracts for the cost certification will be returned on the loan. Agency personnel will utilize exhibit M of this subpart (available in any Agency office) and Form RD 1924-26, “Cost Certification Worksheet,” to assist in the evaluation of the cost certification process.
(H) (Subcontracting development work. (1) Contractors will not be allowed to obtain a profit and overhead unless they are performing actual construction. “Actual construction” means “work” as defined in American Institute of Architects (AIA) documents: “* * * labor, materials, equipment, and services provided by the contractor to fulfill the contractor's obligations.” Under this definition, contractors who choose to subcontract out construction of the project to another contractor will not obtain a builder's fee (general overhead and profit) when:
(i) More than 50 percent of the contract sum in the construction contract is subcontracted to one subcontractor, material supplier, or equipment lessor, and/or
(ii) Seventy-five percent or more with three or fewer subcontractors, material suppliers and/or equipment lessors.
(2) Note: If two or more subcontractors have common ownership, they are considered as one subcontractor.
(3) How to apply rule:
(i) The 50 percent rule will apply when division of the amount of the largest subcontract by the contract sum of the construction contract results in more than 50 percent.
(ii) The 75 percent rule will apply when division of the sum of the amounts of the three largest subcontracts by the contract sum of the construction contract results in 75 percent or more.
(vi) Method of payments. Partial payments may be requested in accordance with the terms of the construction contract on Form RD 1924-18, “Partial Payment Estimate,” or other professionally recognized form that contains the architect's certification, approval of the owner, and conditional acceptance of the Agency as shown in Form RD 1924-18.
(A) If interim financing is available at reasonable rates and terms for the construction period, such financing shall be obtained. exhibit B of subpart E of part 1944 of this chapter shall be used to inform the interim lender that the Agency will not close its loan until the project is substantially complete, ready for occupancy, evidence is furnished indicating that all bills have been paid or will be paid at loan closing for work completed on the project, all inspections have been completed and all required approvals have been obtained from municipal and governmental authorities having jurisdiction over the project.
Upon presentation of proper partial payment estimates approved by the applicant and accepted by the Agency, the interim lender may advance construction funds in accordance with the payment terms of the contract. It is suggested that partial payments not exceed 90 percent of the value of work in place and materials suitably stored on site.
(vii) Exception to competitive bidding—(A) For all applicants. An applicant may negotiate a construction contract provided the State Director grants an exception and documentation shows that:
(1) The contract price is competitive with other projects similar in construction and design being built in the area.
(2) The proposed contractor is experienced in construction of projects of similar size, scope, and complexity, and is recognized as a reliable builder.
(3) The proposed development work meets all requirements of this subpart.
(4) If appropriate for nonprofit organizations and public bodies, the applicant provides a copy of a duly authorized resolution by its governing body requesting the Agency to permit awarding the construction contract without formal bidding.
(5) The applicant is permitted by state law, local law and/or organizational by-laws to negotiate a construction contract.
(6) The requirements of paragraphs (e)(1) (ii), (iii), (iv) and (v) of this section are met.
(B) In considering an exception to competitive bidding, the following additional steps will be taken in all cases.
(1) If, after a full review of the case documents by the appropriate members of the State Office staff, the State Director determines that the requirements have been met and the costs are reasonable, an exception to competitive bidding may be granted. Written documentation of the State Office review results will be placed in the application file.
(2) If after the full review by the State Office staff, the State Director determines that the negotiated contract price is not competitive with other similar projects in construction and design being built in the area, the applicant will be requested to competitively bid the construction of the project in accordance with paragraph (e)(1)(i) of this section.
(3) If there is no agreement by the Agency and the applicant as to the construction cost, the State Director will cease any further action on the preapplication and inform the applicant of the right to appeal in accordance with subpart B of part 1900 of this chapter.
(viii) Exception to contract method—public body. With the approval of the National Office, the State Director may grant to a public body an exception to the requirement for using contract method construction under the following circumstances:
(C) That applicant submits a written request to the District Director indicating:
(1) The scope of work and construction timetable;
(2) What phases of work can be contracted and what cannot;
(3) Why is it not practicable to contract all phases;
(4) Management ability and employee qualifications for performing the work;
(5) Proposed method of fund control and frequency of payments;
(6) How changes in scope of work and construction timetable will be approved; and,
(7) Proposed method of certifying progress and requesting payments.
(2) Owner-builder method. This method of development is used only when requested by profit or limited profit RRH applicants when the applicant or any of its controlling principals (such as stockholders, members, partners other than limited partners, directors, or officers), are general contractors by profession, and will serve as the builder of the project without a written construction contract. The State Director may make an exception to the contract method of construction and authorize proceeding by the owner-builder method of construction in accordance with the provisions of this section if the amount of the loan(s) does not exceed the State Director's approval authority. For projects over the State Director's authority, prior written consent of the National Office is required. In such cases, the drawings, specifications, cost estimates, copy of the State Architect/Engineer's review and detailed information on the applicant's qualifications will be submitted to the National Office along with the State Director's recommendations.
(i) The applicant's request to construct a project by the owner-builder method of construction shall be in the form of a letter giving specific and detailed information concerning the owner-builder's proposal, and the qualifications and past experience of the owner-builder. The following information must be included with the request:
(ii) In order to grant an exception to the contract method of construction and proceed with the owner-builder method of construction, the State Director must determine that the following conditions exist:
(iii) In addition to the requirements for the State Director to authorize the owner-builder method of construction as indicated in § 1924.13(e)(2) (i) and (ii) of this subpart, the following additional steps will be taken by the State Director.
(viii) The applicant/owner-builder and any subcontractor, material supplier, or equipment lessor sharing an identity of interest as defined in § 1924.4(i) of this subpart must each provide certification as to the actual cost of the work performed in connection with the construction of the project on Form RD 1924-13 prior to final payment. The construction costs, as reported on Form RD 1924-13, must be audited by a CPA, or LPA licensed on or before December 31, 1970, in accordance with Government Auditing Standards, and certain agreed upon procedures (available in any Agency office) performed in accordance with Attestation Standards. In some cases, FmHA or its successor agency under Public Law 103-354 will contract directly with a CPA or LPA for the cost certification. In that event, documentation necessary to have the costs of construction certified by an Agency contractor that they were the actual costs of the work performed, as reported on Form RD 1924-13, will be provided. Funds which were included in the loan for cost certification and which are ultimately not needed because Agency contracts for the cost certification will be returned on the loan.
(C) Subcontracting development work.
(1) Owner-builders will not be allowed to obtain a profit and overhead unless they are performing actual construction. “Actual construction” means “work” as defined in AIA documents: “* * * labor, materials, equipment, and services provided by the contractor to fulfill the contractor's obligations.” Under this definition, owner-builders who choose to subcontract out construction of the project to another contractor will not obtain a builder's fee (general overhead and profit) when:
(i) More than 50 percent of the total cost of the building construction is subcontracted to one subcontractor, material supplier, or equipment lessor, and/or
(ii) Seventy-five percent or more with three or fewer subcontractors, material suppliers, and/or equipment lessors.
(2) Note: If two or more subcontractors have common ownership, they are considered as one subcontractor.
(3) How to apply rule:
(i) The 50 percent rule will apply when division of the amount of the largest subcontract by the total amount of the building cost results in more than 50 percent.
(ii) The 75 percent rule will apply when division of the sum of the amounts of the three largest subcontracts by the total building cost results in 75 percent or more.
(ix) Requests for payment for work performed by the owner-builder method, shall be permitted to the Agency District Director for review and approval prior to each advance of funds in order to insure that funds are used for authorized purposes. Requests for payment shall be made on Form RD 1924-18 or other professionally recognized form containing the following certification to the Agency:
The undersigned certifies that the work has been carefully inspected and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. (Name of Architect) By: (Title (Date) Approved by Owner's Representative: By: (Title) Accepted by Agency Representative: By: (Title) The review and acceptance of partial payment estimates by the Agency does not attest to the correctness of the quantities shown or that the work has been performed in accordance with the plans and specifications.
[52 FR 8002, Mar. 13, 1987; 52 FR 26139, July 13, 1987, as amended at 53 FR 2155, Jan. 26, 1988; 59 FR 6882, Feb. 14, 1994; 61 FR 56116, Oct. 31, 1996]