(b) Certification borrowers, shall submit and obtain RUS approval of a work plan before construction and related engineering begin.
- (1) The work plan shall provide a description of the proposed construction and methods of purchasing in such detail as to enable RUS to monitor the construction program to ensure to its satisfaction that loan purposes are accomplished in an organized construction program.
(2) The work plan shall include the following:
- (i) The names and qualifications of the proposed certification officials defined in § 1753.94(a).
- (ii) A listing of the proposed work projects to accomplish the loan purposes showing the estimated cost, method of performing the construction, and the proposed commencement and completion dates for each work project. The proposed work projects shall be summarized on RUS Form 157, Construction Work Plan and Cost Distribution, or a form providing essentially the same information.
- (iii) The proposed source of funds for meeting cost overruns if the total estimated cost of work projects exceeds the loan budget.
- (iv) A statement signed by the borrower's certification officials and the GFR that the work plan is accurate and complete.