(a) General.
(1) Prior to the preparation of P&S for the construction project:
- (i) A review shall be made of the outside plant requirements, and the Loan Design (LD) shall be revised to reflect any needed changes (See § 1753.3).
- (ii) Deviations from the approved LD (7 CFR part 1737) must be approved by RUS (See § 1753.3).
(2) The standard RUS specifications required for construction of outside plant facilities are:
- (i) RUS Form 515a (Bulletin 345-150)—Specifications and Drawings for Construction of Direct Buried Plant.
- (ii) RUS Form 515c (Bulletin 345-151)—Specifications and Drawings for Conduit and Manhole Construction.
- (iii) RUS Form 515d (Bulletin 345-152)—Specifications and Drawings for Underground Cable Installation.
- (iv) RUS Form 515f (Bulletin 345-153)—Specifications and Drawings for Construction of Pole Lines and Aerial Cables.
- (v) RUS Form 515g (Bulletin 345-154)—Specifications and Drawings for Service Entrance and Station Protector Installation.
(b) Preparation of plans and specifications. Each set of plans and specifications shall include:
- (1) RUS Contract Form 515, “Telephone System Construction Contract (Labor and Materials).”
- (2) The specifications described in paragraph (a)(2) of this section as specified by the borrower in the RUS Contract Form 515.
- (3) Description of special assembly units and guide drawings, if any.
- (4) Key, detail, and cable layout maps.
- (5) RUS Contract Form 787, “Supplement A to Construction Contract, RUS Contract Form 515,” when the borrower proposes to provide any materials to the contractor. The borrower shall not order materials for a contractor without RUS approval. In such cases the borrower must attach Form 787 and a “List of Owner's Materials on Hand” and/or a “List of Materials Ordered by Owner but Not Delivered” to contract Form 515 (See § 1753.48(f) of this part). Any materials furnished under Supplement A shall be listed in RUS Bulletin 344-2 unless special RUS approval has been received by the borrower to use unlisted materials.
(c) Submission of plans and specifications to RUS.
- (1) If the project does not exceed $500,000 or 25% of the loan, whichever is less, the borrower shall furnish GFR one set of P&S. The borrower may then proceed with procurement in accordance with § 1753.48.
- (2) If the project exceeds $500,000 or 25% of the loan, whichever is less, RUS approval of P&S is required. Two sets of P&S shall be furnished to GFR. RUS will return one set to the borrower upon notice of approval. The borrower may then proceed with procurement in accordance with § 1753.48.
[54 FR 39267, Sept. 25, 1989. Redesignated at 55 FR 39397, Sept. 27, 1990, 55 FR 53488, Dec. 31, 1990, as amended at 64 FR 16609, Apr. 6, 1999]