7 C.F.R. § 1753.39
Closeout of Equipment Contract, RUS Contract Form 395 (RUS Contract Form 395) (including or not including installation) shall be conducted as follows:
(d) Partial Closeout Procedure. Under conditions set forth in RUS Contract Form 395, a contractor may, when approved by the borrower, receive payment in full for central offices and their respective associated remote switching terminals upon completion of the installation without awaiting completion of the project. The contractor is to receive such payment, according to procedures contained in the applicable sections of RUS Contract Form 395. In addition to complying with the appropriate partial closeout procedure contained in RUS Contract Form 395, the borrower shall:
(e) Final contract closeout procedure. The documents required for the final closeout of the equipment contract, RUS Contract Form 395 with or without installation, are listed in the Table 1 to paragraph (e), which also indicates the number of copies and their distribution.
| RUS Form No. | Description | Number of copies prepared by | Distribution | ||
|---|---|---|---|---|---|
| Seller | Engineer | Buyer | Seller | ||
| 213 | Certificate (Buy American) | 1 | 1 | ||
| 238 | Construction or Equipment Contract Amendment (If not previously submitted, send to RUS for approval) | 3 sent to RUS | 1 from RUS | 1 from RUS. | |
| 395a | Certificate of Completion for Equipment Contract (Including Installation) | 2 | 1 | 1. | |
| 395b | Certificate of Completion for Equipment Contract (Not Including Installation) | 2 | 1 | 1. | |
| 395c | Certificate of Contractor and Indemnity Agreement (Use only for installation contracts) | 1 | 1 | ||
| None | Report in writing, including all measurements, any acceptance test report and other information required under Part II of the applicable specifications (Form 395d may be used) | 1 | 1 | ||
| None | Set of maintenance recommendations for all equipment furnished under the contract | 1 | 1 |
[81 FR 71583, Oct. 18, 2016]