7 C.F.R. § 1753.30
(b) RUS Form 257 Contract.
(c) Upon completion of force account construction, the borrower shall:
(2) Complete, with the assistance of its architect or engineer, the documents listed in the following table that are required for the closeout of force account construction.
| RUS Form No. | Description | Use with | No. of copies prepared by | Distribution | |||
|---|---|---|---|---|---|---|---|
| Contract | Force account | Contractor | Architect/engineer | Borrower | Contractor | ||
| 238 | Construction or Equipment Contract Amendment (if not previously submitted, send to RUS for approval) | X | (3) | (to RUS) | (to RUS) | ||
| 181 | Certificate of Completion (contract construction) 1 | X | 2 | 1 | 1 | ||
| 231 | Certificate of Contractor | X | 1 | 1 | |||
| 224 | Waiver and Release of Lien From Each Supplier | X | 1 | 1 | |||
| 213 | Certificate (buy American) | X | 1 | 1 | |||
| None 2 | “As Built” Plans and Specifications | X | X | 1 | 1 | ||
| None | Guarantees, Warranties, Bonds, Operating or Maintenance Instructions, etc | X | 1 | 1 | |||
| None | Architect/Engineer seismic safety certification | X | X | 2 | 1 | 1 | |
| 1 Cost of materials and services furnished by borrower are not to be included in Total Cost on RUS Form 181. | |||||||
| 2 When only minor changes were made during construction, two copies of a statement to that effect from the Architect will be accepted instead of the “as built” Plans and Specifications. |
[54 FR 39267, Sept. 25, 1989. Redesignated at 55 FR 39396, Sept. 27, 1990, as amended at 59 FR 43717, Aug. 25, 1994; 64 FR 16606, Apr. 6, 1999]