7 C.F.R. § 789.12
(a) Each rated order must include:
(4) A statement as follows:
(i) A statement that reads:
This is a rated order certified for national defense use, and you are required to follow all the provisions of the Agriculture Priorities and Allocations System regulation in 7 CFR part 789.
(ii) If the rated order is placed in support of emergency preparedness requirements and expedited action is necessary and appropriate to meet these requirements, the following sentences should be added following the statement specified in paragraph (a)(4)(i) of this section:
This rated order is placed for the purpose of emergency preparedness. It must be accepted or rejected within six (6) hours after receipt of the order if the order is issued in response to a hazard that has occurred; or within the greater of twelve (12) hours or the time specified in the order, if the order is issued to prepare for an imminent hazard, in accordance with 7 CFR 789.13(e).