(b) Definitions. As used in this section:
Acquisition means obtaining supplies or services through a purchase or lease, regardless of whether the supplies or services are already in existence or must be developed, created or evaluated.
Advance Planning Document for project planning or Planning APD (APD or PAPD) means a brief written plan of action that requests FFP to accomplish the planning activities necessary for a State agency to determine the need for, feasibility of, projected costs and benefits of an IS equipment or services acquisition, plan the acquisition of IS equipment and/or services, and to acquire information necessary to prepare an Implementation APD.
Advance Planning Document Update (APDU) means a document submitted annually (Annual APDU) by the State agency to report the status of project activities and expenditures in relation to the approved Planning APD or Implementation APD; or on an as needed basis (As Needed APDU) to request funding approval for project continuation when significant project changes occur or are anticipated.
Commercial Off-the-Shelf (COTS) means proprietary software products that are ready-made and available for sale to the general public at established catalog or market prices in which the software vendor is not positioned as the sole implementer or integrator of the product.
Enhancement means modifications which change the functions of software and hardware beyond their original purposes, not just to correct errors or deficiencies which may have been present in the software or hardware, or to improve the operational performance of the software or hardware. Software enhancements that substantially increase risk or cost or functionality will require submission of an IAPD or an As Needed IAPDU.
Implementation Advance Planning Document or Implementation APD (IAPD) means a written plan of action requesting FFP to acquire and implement information system (IS) services and/or equipment. The Implementation APD includes the design, development, testing and implementation phases of the project.
Information System (IS) means a combination of hardware and software, data and telecommunications that performs specific functions to support the State agency, or other Federal, State or local organization.
Project means a related set of information technology related tasks, undertaken by a State, to improve the efficiency, economy and effectiveness of administration and/or operation of its human services programs. A project may also be a less comprehensive activity such as office automation, enhancements to an existing system, or an upgrade of computer hardware.
Request for Proposal (RFP) means the document used for public solicitations of competitive proposals from qualified sources as outlined in § 277.14(g)(3).
(c) Requirements for FNS prior approval of IS projects—(1) General prior approval requirements. The State agency shall request prior FNS approval by submitting the Planning APD, the Implementation APD, an APD Update, the draft acquisition instrument, and/or the justification for the sole source acquisition if applicable, as specified in paragraph (c)(2) of this section. A State agency must obtain written approval from FNS to receive FFP of any of the following activities:
(2) Specific prior approval requirements.
(i) For IS projects which require prior approval, as specified in paragraph (c)(1) of this section, the State agency shall obtain the prior written approval of FNS for:
(ii) For IS equipment and services acquisitions requiring prior approval as specified in paragraph (c)(1) of this section, prior approval of the following documents associated with such acquisitions is also required:
(iii) Procurement requirements.
(3) Document submission requirements.
(i) For IS projects requiring prior approval as specified in paragraphs (c)(1) and (c)(2) of this section, the State agency shall submit the following documents to FNS for approval:
(e) Service agreements. The State agency shall execute service agreements when IS services are to be provided by a State central IT facility or another State or local agency. Service Agreement means the document signed by the State or local agency and the State or local central IT facility whenever an IT facility provides IT services to the State or local agency. Service agreements shall:
(f) Conditions for receiving Federal financial participation (FFP)—(1) A State agency may receive FFP at the 50 percent reimbursement rate for the costs of planning, design, development or installation of IS and information retrieval systems if the proposed system will:
(2) Pre-implementation. The State agency must demonstrate through thorough testing that the system meets all program functional and performance requirements. FNS may require a pre-implementation review of the system to validate system functionality prior to State agency testing.
(i) Testing. The State agency must provide a complete test plan prior to the start of the testing phase. The State agency must provide documentation to FNS of the results of User Acceptance Testing (UAT) before the system is piloted in a production environment. FNS concurrence to advance from testing to pilot is a condition for continued FFP. All aspects of program eligibility must be tested to ensure that the system makes accurate eligibility determinations in accordance with federal statutes and regulations and approved State policies, and that system functionality meets the required functional specifications. The State agency shall describe how all system testing will be conducted and the resources to be utilized in order to verify the system complies with SNAP requirements, system design specifications, and performance standards including responsiveness, usability, capacity and security. Testing includes but is not limited to unit testing, integration testing, performance testing, end-to-end testing, UAT and regression testing. During UAT detailed scripts covering all areas of program functionality shall be used so that any errors identified can be replicated, corrected and re-tested. At a minimum, the Test Plan shall address:
(1) The State agency must submit a written request to FNS prior to the acquisition of any IS equipment or services. The written request shall include:
(2) Upon receipt of a written request for emergency acquisition FNS shall provide a written response to the State agency within 14 days. The FNS response shall:
(2) Cost identification for purposes of FFP claims. State agencies shall assign and claim the costs incurred under an approved APD in accordance with the following criteria:
(l) Ownership rights—(1) Software.
(2) Information security program. State agencies shall implement and maintain a comprehensive Security Program for IS and installations involved in the administration of the SNAP. Security Programs shall include the following components:
(ii) Establishment of a security plan and, as appropriate, policies and procedures to address the following areas of IS security:
[79 FR 12, Jan. 2, 2014, as amended at 81 FR 66499, Sept. 28, 2016]