49 C.F.R. § 1155.26
(a) Schedule.
(2) At least 45 days prior to filing of application—Environmental Report (and/or Historic Report, if applicable) filed and environmental process initiated pursuant to 49 CFR 1155.24. Within 30 days prior to filing of application—Notice of Intent filed with the Board pursuant to the deadlines and requirements described in 49 CFR 1155.20(b)(3).
(b) Standard for review.
(4) The Board will reject an application from a person who is not a rail carrier, but is instead operating on behalf of a rail carrier unless;
(5) The Board will issue a land-use-exemption permit to an applicant that has received an unsatisfactory result from a state, local or municipal authority affecting the siting of the facility only if it finds that the laws, regulations, or other requirements affect the siting of the facility, on their face or as applied, either;
(c) Considerations. As required by 49 U.S.C. 10909(d), the Board will consider and give due weight to the following, as applicable: