(a) Prior to commencing revenue operations, the railroad shall conduct tests of the trainsets throughout the system to—
- (1) Verify mechanical positioning of the overhead catenary system; and
- (2) Verify performance of the trainset, track, and signal and trainset control systems.
(b) The railroad shall demonstrate safe operation of the system during normal and degraded-mode operating conditions. At a minimum, the following operation tests shall be performed:
- (1) Slow-speed operation of a trainset;
- (2) Verification of correct overhead catenary and pantograph interaction;
- (3) Verification of trainset clearance at structures and passenger platforms;
- (4) Incremental increase of trainset speed;
- (5) Performance tests on trainsets to verify braking rates in accordance with § 299.409;
- (6) Verification of vehicle noise;
- (7) Verification of correct vehicle suspension characteristics;
- (8) Vehicle/track system qualification as defined in § 299.609;
- (9) Load tests with vehicles to verify relay settings and signal and communication system immunization;
- (10) Monitoring of utility supply circuits and telephone circuits to ensure the adequacy of power supplies, and to verify that transient-related disturbances are within acceptable limits;
- (11) Verification of vehicle detection due to shunting of signal system circuits;
- (12) Verification of safe operation of the signal and trainset control system as required by subpart B of this part;
- (13) Tests of trainset radio reception during system-wide vehicle operation; and
- (14) Verification of electromagnetic interference/electromagnetic compatibility between various subsystems.