Plastic service lines installed by trenchless excavation must comply with the following:
- (a) Each operator shall take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and structures at the time of installation.
- (b) For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by § 192.3, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.
[Amdt. 192-124, 83 FR 58719, Nov. 20, 2018]